Block 0441A, lot 002

269 Avila St

City’s use
Multi-Family Residential
Built
1926
Stories
2
Units
2
Rooms
6 bedrooms, 4 bathrooms
Building
2,485 sq ft
Lot
2,504 sq ft
Zoning
RH1
Construction type
D

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

14 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Aug 22, 2020Completed
final sign-off Jan 2021
269 Avila StControl Fire Inc.as-built plan submittal requested by inspector to be done before final inspection. changes include: pipe rerouting to reflect installation in the field & riser manifold location moved. fire pa #202001212287 & bldg pa #201805240036.
Details
Permit
202008222449
Status
complete
Filed
Aug 22, 2020
Permit issued
Aug 31, 2020
Final sign-off
Jan 25, 2021
Declared cost
$9,699
Address
269 Avila St

as-built plan submittal requested by inspector to be done before final inspection. changes include: pipe rerouting to reflect installation in the field & riser manifold location moved. fire pa #202001212287 & bldg pa #201805240036.

Open the permit page

$9,699
Jun 12, 2020Never finaled
issued Jul 2020, no final
269 Avila Ststreet space
Details
Permit
M1210207
Status
issued
Filed
Jun 12, 2020
Permit issued
Jul 2, 2020
Address
269 Avila St

street space

Open the permit page

Jan 21, 2020Completed
final sign-off Oct 2020
269 Avila StControl Fire Inc.ref pa# 201805240036; installation of new overhead fire protection sprinkler system of 22 heads including underground.
Details
Permit
202001212287
Status
complete
Filed
Jan 21, 2020
Permit issued
Feb 13, 2020
Final sign-off
Oct 28, 2020
Declared cost
$9,699
Address
269 Avila St

ref pa# 201805240036; installation of new overhead fire protection sprinkler system of 22 heads including underground.

Open the permit page

$9,699
Oct 24, 2019Never finaled
issued Oct 2019, no final
269 Avila Ststreet space
Details
Permit
M1157887
Status
issued
Filed
Oct 24, 2019
Permit issued
Oct 24, 2019
Address
269 Avila St

street space

Open the permit page

Sep 13, 2019Completed
final sign-off Jan 2021
269 Avila StAlli Construction Increvision to 201805240036 revise layout of proposed dwelling unit to eliminate separation btw sleeping & living rm. revise bath layout, laundry/closet layout & bike parking location and patio doors unit a
Details
Permit
201909131540
Status
complete
Filed
Sep 13, 2019
Permit issued
Oct 24, 2019
Final sign-off
Jan 28, 2021
Address
269 Avila St

revision to 201805240036 revise layout of proposed dwelling unit to eliminate separation btw sleeping & living rm. revise bath layout, laundry/closet layout & bike parking location and patio doors unit a

Open the permit page

May 9, 2019Never finaled
issued May 2019, no final
269 Avila Ststreet space
Details
Permit
M1078547
Status
issued
Filed
May 9, 2019
Permit issued
May 9, 2019
Address
269 Avila St

street space

Open the permit page

Mar 22, 2019Completed
final sign-off Jan 2021
269 Avila StAlli Construction Incseismic strengthening in accordance with sf existing building code 407.4.1 and 301.2 ref 201805240036
Details
Permit
201903226029
Status
complete
Filed
Mar 22, 2019
Permit issued
May 9, 2019
Final sign-off
Jan 28, 2021
Declared cost
$40,000
Address
269 Avila St

seismic strengthening in accordance with sf existing building code 407.4.1 and 301.2 ref 201805240036

Open the permit page

$40,000
May 24, 2018Completed
final sign-off Jan 2021
269 Avila StAlli Construction Incaddition of accesory dwelling unit per ordinance 162-16. **maher n/a**
Details
Permit
201805240036
Status
complete
Filed
May 24, 2018
Permit issued
May 9, 2019
Final sign-off
Jan 28, 2021
Declared cost
$78,000
Address
269 Avila St

addition of accesory dwelling unit per ordinance 162-16. **maher n/a**

Open the permit page

$78,000
Mar 2, 2018Completed
final sign-off May 2018
269 Avila StAlli Construction Inccomply with nov complaint #201721221; remove unpermitted bathroom at ground floor,recently constructed, remove heat source, revert 2 rooms back to storage per plan.
Details
Permit
201803022712
Status
complete
Filed
Mar 2, 2018
Permit issued
Mar 9, 2018
Final sign-off
May 29, 2018
Declared cost
$1,000
Address
269 Avila St

comply with nov complaint #201721221; remove unpermitted bathroom at ground floor,recently constructed, remove heat source, revert 2 rooms back to storage per plan.

Open the permit page

$1,000
Jan 17, 2018Expired or cancelled
withdrawn Mar 2018
269 Avila StAlli Construction Incremoval of non-load bearing walls. install nw non-load bearing walls. install nw cabinets, nw flooring, partial drywall & paint, & nw plumbing fixtures.
Details
Permit
201801178833
Status
withdrawn
Filed
Jan 17, 2018
Declared cost
$30,000
Address
269 Avila St

removal of non-load bearing walls. install nw non-load bearing walls. install nw cabinets, nw flooring, partial drywall & paint, & nw plumbing fixtures.

Open the permit page

$30,000
Nov 29, 2017Completed
final sign-off Jun 2018
269 Avila StAlli Construction Inc3rd fl - remove non-bearing wall and add new walls. maher n/a
Details
Permit
201711295054
Status
complete
Filed
Nov 29, 2017
Permit issued
Nov 29, 2017
Final sign-off
Jun 19, 2018
Declared cost
$20,000
Address
269 Avila St

3rd fl - remove non-bearing wall and add new walls. maher n/a

Open the permit page

$20,000
Jun 30, 2017Completed
final sign-off Jun 2018
269 Avila StAlli Construction Incremodel kitchens both units , baths, living rms. drywall patches as needed, cabinets, lighting,r&r all appliances,floor, tile, door hardware, baseboard, paint
Details
Permit
201706300843
Status
complete
Filed
Jun 30, 2017
Permit issued
Jul 3, 2017
Final sign-off
Jun 19, 2018
Declared cost
$300,000
Address
269 Avila St

remodel kitchens both units , baths, living rms. drywall patches as needed, cabinets, lighting,r&r all appliances,floor, tile, door hardware, baseboard, paint

Open the permit page

$300,000
Jul 23, 2009Completed
final sign-off Nov 2009
269 Avila Strepair lightwell stairs connecting grade level & level one, less than 50% repair in kind, any new replaced component shall comply w/ current code excedtrer.
Details
Permit
200907233354
Status
complete
Filed
Jul 23, 2009
Permit issued
Jul 23, 2009
Final sign-off
Nov 13, 2009
Declared cost
$15,000
Address
269 Avila St

repair lightwell stairs connecting grade level & level one, less than 50% repair in kind, any new replaced component shall comply w/ current code excedtrer.

Open the permit page

$15,000
Jan 20, 2009Completed
final sign-off Jan 2010
269 Avila Streplace rear yard 2nd means of egress stair.
Details
Permit
200901200406
Status
complete
Filed
Jan 20, 2009
Permit issued
Jul 27, 2009
Final sign-off
Jan 6, 2010
Declared cost
$15,000
Address
269 Avila St

replace rear yard 2nd means of egress stair.

Open the permit page

$15,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Alli Construction Inc (7), Control Fire Inc. (2)
Architects
Jamie Mastro (2), C Swason
Engineers
Joe Kon (2)

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover two-family buildings like this one.