43 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 23, 2009 | Completed final sign-off Jul 2010 | 942 Market St | Jemcom, N S A Wireless Inc | 6 atennas to be added and swapped.Details
6 atennas to be added and swapped. | $8,500 |
| Jul 9, 2009 | Never finaled issued Jul 2009, no final | 938 Market St | Regency Crown 2000 General Contracting | t.i. on ground floor. add 1 duct detector, 3 speakers/strobes (1) light to (e) graphic anunciator.Details
t.i. on ground floor. add 1 duct detector, 3 speakers/strobes (1) light to (e) graphic anunciator. | $3,000 |
| Jun 30, 2009 | Never finaled issued Jul 2009, no final | 938 Market St | Regency Crown 2000 General Contracting | anchored shelving for retail and storage. t.i approved under pa# 2009.01.13.0166Details
anchored shelving for retail and storage. t.i approved under pa# 2009.01.13.0166 | $10,000 |
| Jun 26, 2009 | Completed final sign-off Aug 2009 | 938 Market St | Simplex Grinnell | add new quick response fire and relocate new quick response fire sprinklers to accomondate new ceiling plan under ref pa# 2008.10.06.3480. work on the 1st floor.Details
add new quick response fire and relocate new quick response fire sprinklers to accomondate new ceiling plan under ref pa# 2008.10.06.3480. work on the 1st floor. | $3,800 |
| Mar 18, 2009 | Completed final sign-off Mar 2009 | 942 Market St | R. C. Construction | bathroom addition to core bldg. space. adding (1) speaker/strobe per nfpa. the vacant space will be under separate permit. ref. appl.#2008/1006/3480.Details
bathroom addition to core bldg. space. adding (1) speaker/strobe per nfpa. the vacant space will be under separate permit. ref. appl.#2008/1006/3480. | $800 |
| Mar 2, 2009 | Completed final sign-off Aug 2009 | 938 Market St | Sign & Sign Again | install 12ft. long electrical sign above doorway.Details
install 12ft. long electrical sign above doorway. | $2,500 |
| Feb 9, 2009 | Completed final sign-off Mar 2009 | 942 Market St | Golden Bear Fire Protect. | 1st floor-add 1 sprinkler in new restroomsDetails
1st floor-add 1 sprinkler in new restrooms | $3,500 |
| Jan 20, 2009 | Completed final sign-off Mar 2009 | 942 Market St | S & R Drywall Incorporated | remove & replace water damaged drywall. sprnklr broke on the 7th floor & damaged drywall on approx. 6th floors in several units and corridors. we will be replacing only the water damaged drywall & taping. we will be replacing approx. a 2' strip around the bottom of some of the walls in several unitsDetails
remove & replace water damaged drywall. sprnklr broke on the 7th floor & damaged drywall on approx. 6th floors in several units and corridors. we will be replacing only the water damaged drywall & taping. we will be replacing approx. a 2' strip around the bottom of some of the walls in several units | $80,000 |
| Jan 13, 2009 | Expired or cancelled expired Apr 2013 | 938 Market St | Regency Crown 2000 General Contracting | soft demo of extg retail and tenant improvment at ground floor. store to put in a new retail store,(radio shack) project includes new fixtures and new lighting and new hvac unit. no exterior work.Details
soft demo of extg retail and tenant improvment at ground floor. store to put in a new retail store,(radio shack) project includes new fixtures and new lighting and new hvac unit. no exterior work. | $80,000 |
| Dec 1, 2008 | Completed final sign-off Oct 2009 | 942 Market St | replace e wood fixed windows on market st and mason st facades and lightwell with new operable windowsDetails
replace e wood fixed windows on market st and mason st facades and lightwell with new operable windows | $42,000 | |
| Nov 17, 2008 | Completed final sign-off Nov 2008 | 940 Market St | Signawest Systems Inc | extend (e) building voice evacuation system & visual notification to subway tenant. as built to 200809030651.Details
extend (e) building voice evacuation system & visual notification to subway tenant. as built to 200809030651. | |
| Nov 3, 2008 | Never finaled issued Nov 2008, no final | 30 Mason St | to verify addresses for block 0341 lot 005 (#30 & 32 mason street) (#938, 940 and 942 market street)Details
to verify addresses for block 0341 lot 005 (#30 & 32 mason street) (#938, 940 and 942 market street) | ||
| Oct 6, 2008 | Completed final sign-off Mar 2009 | 942 Market St | R. C. Construction | accessible restroom addition to unimproved tenatn space, new partition walls, fixtures and finishesDetails
accessible restroom addition to unimproved tenatn space, new partition walls, fixtures and finishes | $35,000 |
| Sep 15, 2008 | Completed final sign-off Dec 2008 | 940 Market St | Aquamatic Fire Protection | install 20 fire sprinklers for a tenant improvementDetails
install 20 fire sprinklers for a tenant improvement | $4,500 |
| Sep 3, 2008 | Never finaled issued Sep 2008, no final | 940 Market St | Signawest Systems Inc | provide a manual fire alarm system to subway store. subway facp shall be monitored by the bldg's (e) siemens facp.Details
provide a manual fire alarm system to subway store. subway facp shall be monitored by the bldg's (e) siemens facp. | $1,050 |
| Apr 4, 2008 | Completed final sign-off Apr 2008 | 942 Market St | renew appl#200706255029 for final inspection.Details
renew appl#200706255029 for final inspection. | ||
| Jan 30, 2008 | Completed final sign-off Jun 2008 | 942 Market St | ti on ground floor to construct a new demising wall to separate two comercial spaces. mep under separate permit. accessibility to be provide with t.i. per sfbc ab-017.Details
ti on ground floor to construct a new demising wall to separate two comercial spaces. mep under separate permit. accessibility to be provide with t.i. per sfbc ab-017. | $11,000 | |
| Jan 16, 2008 | Completed final sign-off Nov 2008 | 940 Market St | Alves Bayarea Construction | existing subway, to remain interior finishes, bldg remodel, reinstall equipment and some plumbing, electrical, wall paper. tile work. mechanical. at subway restaurant.Details
existing subway, to remain interior finishes, bldg remodel, reinstall equipment and some plumbing, electrical, wall paper. tile work. mechanical. at subway restaurant. | $68,000 |
| Dec 21, 2007 | Completed final sign-off Jan 2008 | 942 Market St | for documentation purpose only. revise pa# 2003/08/05/1236. confirm that residential units are not adaptable per chapter 11a of 2001 cbc because bldg was built before 1978.Details
for documentation purpose only. revise pa# 2003/08/05/1236. confirm that residential units are not adaptable per chapter 11a of 2001 cbc because bldg was built before 1978. | ||
| Nov 19, 2007 | Completed final sign-off Jan 2008 | 942 Market St | 7 new steel posts to attach to eisting steel sidewalk beams sidewalk replacement under dpw per og1e-0703 no work in residential units.Details
7 new steel posts to attach to eisting steel sidewalk beams sidewalk replacement under dpw per og1e-0703 no work in residential units. | $14,500 | |
| Oct 29, 2007 | Completed final sign-off Jan 2008 | 942 Market St | replacement of structural sidewalk slab on mason street (suplement to dpw street improvement 06ie-0713Details
replacement of structural sidewalk slab on mason street (suplement to dpw street improvement 06ie-0713 | $20,000 | |
| Jul 31, 2007 | Completed final sign-off Aug 2007 | 942 Market St | revision to approved pa# 2003/08/05/1236/s1. relocate standpipe and change sprinkler head and type at lightwellDetails
revision to approved pa# 2003/08/05/1236/s1. relocate standpipe and change sprinkler head and type at lightwell | $5,200 | |
| Jul 18, 2007 | Completed final sign-off Dec 2007 | 942 Market St | revision to approved pa# 2003/0805/1236 s1 to change facade facing market st and mason facade. per planning dept comments. new canopy over louvers and glass doors.Details
revision to approved pa# 2003/0805/1236 s1 to change facade facing market st and mason facade. per planning dept comments. new canopy over louvers and glass doors. | $21,000 | |
| Jun 25, 2007 | Never finaled issued Aug 2007, no final | 942 Market St | exterior building maintenance system (window washing equipment)Details
exterior building maintenance system (window washing equipment) | $15,000 | |
| May 17, 2007 | Completed final sign-off Aug 2007 | 942 Market St | change head of wall detail to install verticlip at each rated wall stud. revision to pa# 200308051236-s1Details
change head of wall detail to install verticlip at each rated wall stud. revision to pa# 200308051236-s1 | $5,000 | |
| Mar 19, 2007 | Completed final sign-off Aug 2007 | 942 Market St | new emergency generator at basement level. new fuel oil system.Details
new emergency generator at basement level. new fuel oil system. | $111,000 | |
| Feb 14, 2007 | Completed final sign-off Aug 2007 | 942 Market St | structural demolition. all disable access and siesmic upgrade will be under app #200308051236 in file, no exterior workDetails
structural demolition. all disable access and siesmic upgrade will be under app #200308051236 in file, no exterior work | $40,000 | |
| Jan 31, 2007 | Never finaled issued Jan 2007, no final | 942 Market St | street space permitDetails
street space permit | ||
| Jan 30, 2007 | Completed final sign-off Dec 2010 | 942 Market St | L.D. Strobel Co Ltd | renewal of pa#2006/01/30/3366 for final inspectionDetails
renewal of pa#2006/01/30/3366 for final inspection | |
| Dec 7, 2006 | Completed final sign-off Aug 2007 | 942 Market St | structural demolition for new light court and new hvac. no exterior work. no build back under this permit. non historic storefront. building permit #200308051236Details
structural demolition for new light court and new hvac. no exterior work. no build back under this permit. non historic storefront. building permit #200308051236 | $75,000 | |
| Dec 5, 2006 | Completed final sign-off Aug 2007 | 942 Market St | facade investigation to determine necessary repairs along mason st clean extg facade and refurbish extg wood. wndws as needed. no other work under this permit. no change to extg facade under this permitDetails
facade investigation to determine necessary repairs along mason st clean extg facade and refurbish extg wood. wndws as needed. no other work under this permit. no change to extg facade under this permit | $25,000 | |
| Jul 14, 2006 | Completed final sign-off Aug 2007 | 942 Market St | interior non-structural soft demo on all floors. all life safety & sprinkler under seperate permit. building construction & change of occupancy under separate permit.Details
interior non-structural soft demo on all floors. all life safety & sprinkler under seperate permit. building construction & change of occupancy under separate permit. | $150,000 | |
| Jan 30, 2006 | Expired or cancelled expired Mar 2007 | 942 Market St | L.D. Strobel Co Ltd | renew appl#200502024662 for final inspectionDetails
renew appl#200502024662 for final inspection | |
| Jul 22, 2005 | Never finaled issued Jul 2005, no final | 942 Market St | street spaceDetails
street space | ||
| Feb 2, 2005 | Expired or cancelled expired Dec 2021 | 942 Market St | L.D. Strobel Co Ltd | replaceing all center antennas-9 total.Details
replaceing all center antennas-9 total. | $2,500 |
| Aug 25, 2004 | Never finaled issued Aug 2004, no final | 942 Market St | street spaceDetails
street space | ||
| Apr 16, 2004 | Never finaled issued Apr 2004, no final | 942 Market St | Edwards Systems Technology Inc/Est Servi | emergency replacemento f nonfunctionals fire alarm panel. replacement of existing facp with exist deDetails
emergency replacemento f nonfunctionals fire alarm panel. replacement of existing facp with exist de | $14,101 |
| Aug 5, 2003 | Never finaled issued May 2007, no final | 942 Market St | conversion of existing office to residential, new seismic upgrade, fire protection, newDetails
conversion of existing office to residential, new seismic upgrade, fire protection, new | $4,000,000 | |
| Apr 11, 2003 | Completed final sign-off May 2003 | 940 Market St | rev. appl#200212133512Details
rev. appl#200212133512 | ||
| Mar 6, 2003 | Completed final sign-off May 2003 | 940 Market St | install duct system (hvac)addt'l work to 200212133512Details
install duct system (hvac)addt'l work to 200212133512 | $5,000 | |
| Jan 29, 2003 | Completed final sign-off May 2003 | 940 Market St | Sunny Neon Sign System | sign permit - electric, wall double faced.Details
sign permit - electric, wall double faced. | $2,000 |
| Dec 13, 2002 | Completed final sign-off Jan 2006 | 940 Market St | convert bicycle shop store into a subway deli sancwich shopDetails
convert bicycle shop store into a subway deli sancwich shop | $46,000 | |
| Feb 23, 2000 | Expired or cancelled expired Jun 2000 | 942 Market St | revision to app #9914139Details
revision to app #9914139 |