Block 0305, lot 006
501 Taylor St
- City’s use
- Multi-Family Residential
- Built
- 1920
- Stories
- 6
- Units
- 81
- Rooms
- 79 bathrooms
- Building
- 46,919 sq ft
- Lot
- 9,452 sq ft
- Zoning
- RC4
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
14 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 10, 2024 | In progress issued Apr 2026 | 501 Taylor St | Diablo Telecom & Construction Inc | att: remove 4 extg antennas and replace with 4 new antennas, remove 3 extg rrus, remove 4 extg frp screens and replace w/ 4 new frp screens; install 4 new batteries inside extg cabinets; install 3 new rectifiers inside extg cabinet.Details
att: remove 4 extg antennas and replace with 4 new antennas, remove 3 extg rrus, remove 4 extg frp screens and replace w/ 4 new frp screens; install 4 new batteries inside extg cabinets; install 3 new rectifiers inside extg cabinet. | $90,000 |
| Feb 23, 2021 | Completed final sign-off May 2021 | 501 Taylor St | Crime Watch Security Sys Llc | voluntary replacement & lf upgrade replace of existing facp ifp-75, replace of existing pull station next to facu, install of new low frequency sounders in common areas replace of existing horn strobes sounders install of new 5496 power supply.Details
voluntary replacement & lf upgrade replace of existing facp ifp-75, replace of existing pull station next to facu, install of new low frequency sounders in common areas replace of existing horn strobes sounders install of new 5496 power supply. | $68,011 |
| Sep 14, 2020 | Completed final sign-off May 2021 | 501 Taylor St | Electric Tech Construction Inc | at&t modification:- remove (1) existing panel antenna per sector, (4) total- remove (1) existing rrus per sector, (4) total -relocate (1) antenna mount on position 1 at beta sector far east as possible-install (1) new panel antenna per sector (4) totalDetails
at&t modification:- remove (1) existing panel antenna per sector, (4) total- remove (1) existing rrus per sector, (4) total -relocate (1) antenna mount on position 1 at beta sector far east as possible-install (1) new panel antenna per sector (4) total | $31,500 |
| Nov 6, 2018 | Completed final sign-off Jun 2019 | 501 Taylor St | Electric Tech Construction Inc | at&t modification - remove and replace 8 (e) antennas with 8 (n) antenas; install 12 (n) rrus; install (n) cabinet; remoe unused equipment; no change to batteries. n/a for maher.Details
at&t modification - remove and replace 8 (e) antennas with 8 (n) antenas; install 12 (n) rrus; install (n) cabinet; remoe unused equipment; no change to batteries. n/a for maher. | $51,000 |
| Jan 19, 2018 | Expired or cancelled withdrawn Jul 2018 | 501 Taylor St | swap (4) panel antennas, remove(4) rrus. remove (1) dus41, install (1) 5216 and (1) xmv unit all inside exiting cabinet. **maher n/a**Details
swap (4) panel antennas, remove(4) rrus. remove (1) dus41, install (1) 5216 and (1) xmv unit all inside exiting cabinet. **maher n/a** | $15,000 | |
| Oct 9, 2014 | Completed final sign-off Dec 2014 | 501 Taylor St | Walgreen Company | revision to 201404233920 to resolve restroom clearance requirements by providing unisex restroom and convert another restroom to unisex. n/a ordinance #155-13Details
revision to 201404233920 to resolve restroom clearance requirements by providing unisex restroom and convert another restroom to unisex. n/a ordinance #155-13 | |
| May 9, 2014 | Completed final sign-off Nov 2014 | 501 Taylor St | Electric Tech Construction Inc | modification to e unmanned att telecommunciation facility consisting of adding 4 new rrus-12 units with a2 modules, 1 new purcell cabinets, 1 new dus 41 unit inside new purcell cabinetDetails
modification to e unmanned att telecommunciation facility consisting of adding 4 new rrus-12 units with a2 modules, 1 new purcell cabinets, 1 new dus 41 unit inside new purcell cabinet | $10,200 |
| Apr 23, 2014 | Completed final sign-off Dec 2014 | 501 Taylor St | Walgreen Company | remodel in existing walgreens. work includes adding a consult room on th esales flr, reworking doors to accomodate consult room, removing low wall behind cash registers & related work associated with these modifications. new reach in refrigerated cases. compliance with ordinance #155-13 not requiredDetails
remodel in existing walgreens. work includes adding a consult room on th esales flr, reworking doors to accomodate consult room, removing low wall behind cash registers & related work associated with these modifications. new reach in refrigerated cases. compliance with ordinance #155-13 not required | $85,000 |
| Nov 4, 2013 | Expired or cancelled cancelled Jan 2026 | 501 Taylor St | revision to 201303252961. modification to original support beams and welds to match onsite conditionsDetails
revision to 201303252961. modification to original support beams and welds to match onsite conditions | $215,000 | |
| Oct 22, 2013 | Completed final sign-off Jun 2014 | 501 Taylor St | Modern Construction Inc | comply with nov #20131844, cosmetic repair to exterior column siding in kind.Details
comply with nov #20131844, cosmetic repair to exterior column siding in kind. | $2,000 |
| Aug 12, 2013 | Never finaled issued Aug 2013, no final | 501 Taylor St | street space and mtaDetails
street space and mta | ||
| Mar 25, 2013 | Completed final sign-off Feb 2014 | 501 Taylor St | Electric Tech Construction Inc | this project involves install of att outdoor panel antennas and ancillary equipment to be mounted on (e) roof and bay penthouse. 315 sf. att equipment cabinets to be installed in (n) equipment shelter on lower roof 102 sf. antenna coaxial transmission lines from rrv to antennas.Details
this project involves install of att outdoor panel antennas and ancillary equipment to be mounted on (e) roof and bay penthouse. 315 sf. att equipment cabinets to be installed in (n) equipment shelter on lower roof 102 sf. antenna coaxial transmission lines from rrv to antennas. | $200,000 |
| Mar 17, 2004 | Never finaled issued Mar 2004, no final | 501 Taylor St | street space permitDetails
street space permit | ||
| Mar 9, 2004 | Completed final sign-off May 2004 | 501 Taylor St | S One Construction | reroofingDetails
reroofing | $80,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Electric Tech Construction Inc (4), Walgreen Company (2), Crime Watch Security Sys Llc, Diablo Telecom & Construction Inc, Modern Construction Inc, S One Construction
- Architects
- Carolyn Jones (2), Michael Wilk (2), Nestor Popowych
- Engineers
- Chris Lee (2), Chris M. Iser, Lewis James Burrows
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.