Block 0296, lot 015
490 Post St
- City’s use
- Commercial Misc
- Built
- 1925
- Stories
- 4
- Building
- 42,539 sq ft
- Zoning
- NA
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
37 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 9, 2023 | Expired or cancelled cancelled Jan 2026 | 490 Post St | new non-bearing partition walls for reception area , exam room, street & lab, staff lounge, new gypsum board ceiling, & sffits accessible restrooms.Details
new non-bearing partition walls for reception area , exam room, street & lab, staff lounge, new gypsum board ceiling, & sffits accessible restrooms. | $480,000 | |
| May 17, 2022 | Expired or cancelled cancelled Jan 2026 | 490 Post St | interior tenant improvement including: install new ramp to valet area. upgrade (e) restroom to pull compliance, construct new private office. under separate permit, upgrade (e) building entry per abe program.Details
interior tenant improvement including: install new ramp to valet area. upgrade (e) restroom to pull compliance, construct new private office. under separate permit, upgrade (e) building entry per abe program. | $45,000 | |
| Jul 16, 2021 | Expired or cancelled cancelled Jan 2026 | 490 Post St | upgrade of (e) building entry per city of s.f. accessible buisiness entry program for (e) parkingg gararge. install power door operator. tenent improvements under separate permite to include: install new pedestrian ramp upgade (e) restroom add new office, meps to be disign build under def permintDetails
upgrade of (e) building entry per city of s.f. accessible buisiness entry program for (e) parkingg gararge. install power door operator. tenent improvements under separate permite to include: install new pedestrian ramp upgade (e) restroom add new office, meps to be disign build under def permint | $45,000 | |
| Apr 1, 2021 | Completed final sign-off Jun 2022 | 490 Post St | Sure Fire Protection | relocate 2 sprinklers for new ceiling heightDetails
relocate 2 sprinklers for new ceiling height | $6,500 |
| Sep 26, 2020 | Never finaled issued Jun 2021, no final | 490 Post St | Cal Builders | accessibility improvement to 490 post st. common area. barrier removalDetails
accessibility improvement to 490 post st. common area. barrier removal | $30,000 |
| Mar 13, 2020 | Never finaled issued Mar 2020, no final | 490 Post St | street spaceDetails
street space | ||
| Mar 13, 2020 | Never finaled issued Mar 2020, no final | 490 Post St | street spaceDetails
street space | ||
| Dec 26, 2019 | Never finaled issued Jan 2020, no final | 490 Post St | street spaceDetails
street space | ||
| Aug 29, 2019 | Never finaled issued Aug 2019, no final | 490 Post St | street spaceDetails
street space | ||
| Feb 26, 2019 | Never finaled issued Feb 2019, no final | 490 Post St | street space w/mtaDetails
street space w/mta | ||
| Sep 18, 2018 | Never finaled issued Sep 2018, no final | 490 Post St | street spaceDetails
street space | ||
| Aug 8, 2018 | Never finaled issued Aug 2018, no final | 490 Post St | street space w/mtaDetails
street space w/mta | ||
| Feb 27, 2018 | Never finaled issued Feb 2018, no final | 490 Post St | street spaceDetails
street space | ||
| Jan 12, 2018 | Never finaled issued Jan 2018, no final | 490 Post St | Everest Waterproofing & Restoration Inc. | street spaceDetails
street space | |
| Nov 20, 2017 | Never finaled issued Nov 2017, no final | 490 Post St | street space permitDetails
street space permit | ||
| Nov 7, 2017 | Never finaled issued Nov 2017, no final | 490 Post St | street spaceDetails
street space | ||
| Oct 10, 2017 | Never finaled issued Oct 2017, no final | 490 Post St | street space w/mtaDetails
street space w/mta | ||
| Aug 9, 2017 | Never finaled issued Aug 2017, no final | 490 Post St | street space permitDetails
street space permit | ||
| Jul 11, 2017 | Never finaled issued Jul 2017, no final | 490 Post St | Everest Waterproofing & Restoration Inc. | street spaceDetails
street space | |
| Mar 10, 2017 | Never finaled issued Mar 2017, no final | 490 Post St | street spaceDetails
street space | ||
| Feb 14, 2017 | Never finaled issued Feb 2017, no final | 490 Post St | street space w/mtaDetails
street space w/mta | ||
| Jan 13, 2017 | Never finaled issued Jan 2017, no final | 490 Post St | streetspaceDetails
streetspace | ||
| Aug 23, 2016 | Never finaled issued May 2017, no final | 490 Post St | street spaceDetails
street space | ||
| Jul 1, 2016 | Never finaled issued Jan 2017, no final | 490 Post St | Johnson Controls Fire | connect 2 each existing manual class iii standpipes at basement to existing fire pump and change out 3-inch dry hose valves to wet 3-inch hose valves at floors w/ psi for 1-1/2 hose valves that are over 100 psi use pressure reducing hose valves.Details
connect 2 each existing manual class iii standpipes at basement to existing fire pump and change out 3-inch dry hose valves to wet 3-inch hose valves at floors w/ psi for 1-1/2 hose valves that are over 100 psi use pressure reducing hose valves. | $31,500 |
| Jun 24, 2016 | Never finaled issued Jun 2016, no final | 490 Post St | street spaceDetails
street space | ||
| Sep 22, 2014 | Never finaled issued Sep 2014, no final | 490 Post St | street space w/mtaDetails
street space w/mta | ||
| Jul 11, 2013 | Never finaled issued Jul 2013, no final | 490 Post St | street space permitDetails
street space permit | ||
| Aug 16, 2011 | Completed final sign-off Sep 2011 | 490 Post St | Starlite Electric Inc. | install (5) ceiling-mounted strobes. (6) wall-mounted strobes, (5) ceiling-mounted speaker strobes on 15th floor.Details
install (5) ceiling-mounted strobes. (6) wall-mounted strobes, (5) ceiling-mounted speaker strobes on 15th floor. | $3,500 |
| Jun 23, 2011 | Completed final sign-off Aug 2011 | 490 Post St | Starlite Electric Inc. | 4th floor-install 4 ceiling mount strobes, install 3 ceiling mount speaker/strobesDetails
4th floor-install 4 ceiling mount strobes, install 3 ceiling mount speaker/strobes | $2,500 |
| Jul 1, 2009 | Never finaled issued Jul 2009, no final | 490 Post St | Ac Electrical Design Inc | submitting as built plans for floors 8,9 & 10 of the 490 post st. t.i. adding (2) smoke detectors, removing (3) relay modules.Details
submitting as built plans for floors 8,9 & 10 of the 490 post st. t.i. adding (2) smoke detectors, removing (3) relay modules. | $1,000 |
| Jun 29, 2009 | Never finaled issued Jul 2009, no final | 490 Post St | Ac Electrical Design Inc | tenant improvement on the 5th. flr. suite 520. adding 1-speaker/strobe, 2-strobes, relocating 1-speaker/strobe, 1-strobe. all work on 5th floor, ste 520.Details
tenant improvement on the 5th. flr. suite 520. adding 1-speaker/strobe, 2-strobes, relocating 1-speaker/strobe, 1-strobe. all work on 5th floor, ste 520. | $1,700 |
| May 7, 2009 | Never finaled issued May 2009, no final | 490 Post St | Ac Electrical Design Inc | tenant improvment on the 8,9,10th floors at 490 post. add 3 power supplies, 3 relay modules, 1 smoke detector, 57 speaker/strobes, 52 strobes, 6 dual sync modulesDetails
tenant improvment on the 8,9,10th floors at 490 post. add 3 power supplies, 3 relay modules, 1 smoke detector, 57 speaker/strobes, 52 strobes, 6 dual sync modules | $10,000 |
| Apr 16, 2009 | Expired or cancelled cancelled Jan 2026 | 490 Post St | revision to application 200808129007. to show as built.Details
revision to application 200808129007. to show as built. | ||
| Aug 12, 2008 | Completed final sign-off Dec 2008 | 490 Post St | Woods Remodeling Inc | #1701 -tenant improvement, add 5 speaker/strobes, 4 strobesDetails
#1701 -tenant improvement, add 5 speaker/strobes, 4 strobes | $2,000 |
| Aug 12, 2008 | Completed final sign-off May 2009 | 490 Post St | Woods Remodeling Inc | #1700 -tenant improvement, add 6 speaker/strobes, 3 strobes, 2 wp speaker/strobesDetails
#1700 -tenant improvement, add 6 speaker/strobes, 3 strobes, 2 wp speaker/strobes | $3,000 |
| Apr 7, 2008 | Expired or cancelled expired Aug 2010 | 490 Post St | Dooher Construction | 9th floor, #910: office tenant improvement to vacant unit of (e) office bldg: remove all existing interior partitions, fixtures, finishes; suspend ceiling & lights to remain. new interior partitions, sink, carpet, paint. relocate existing light fixtures. sprinklers under separate permit.Details
9th floor, #910: office tenant improvement to vacant unit of (e) office bldg: remove all existing interior partitions, fixtures, finishes; suspend ceiling & lights to remain. new interior partitions, sink, carpet, paint. relocate existing light fixtures. sprinklers under separate permit. | $40,000 |
| Mar 26, 2008 | Never finaled issued May 2008, no final | 490 Post St | Woods Remodeling Inc | t.i. on 5th, 6th & 7th floors. adding 3- power supply, 3 relay modules, 57 speakers/strobes, ceil.mnt. 6- speakers/strobes wall mnt, 78 strobes ceil.mnt. 2 speakers.Details
t.i. on 5th, 6th & 7th floors. adding 3- power supply, 3 relay modules, 57 speakers/strobes, ceil.mnt. 6- speakers/strobes wall mnt, 78 strobes ceil.mnt. 2 speakers. | $26,000 |