Block 0033, lot 003
2290 Stockton St
- City’s use
- Multi-Family Residential
- Built
- 1968
- Stories
- 3
- Units
- 170
- Rooms
- 172 bathrooms
- Building
- 131,785 sq ft
- Lot
- 56,715 sq ft
- Zoning
- RM3
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
119 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 15, 2026 | In progress issued Jul 2026 | 2290 Stockton St | Wise Builders Inc | unit #3109: remodel kitchen & bath in kind cabinets & fixtures in same location.Details
unit #3109: remodel kitchen & bath in kind cabinets & fixtures in same location. | $55,000 |
| Aug 13, 2025 | In progress filed Aug 2025, not yet issued | 2210 Stockton St | Allied Fire Protection | administrative permit to obtain job card for building c for fire only permit ref pa 202405021233Details
administrative permit to obtain job card for building c for fire only permit ref pa 202405021233 | |
| Jul 8, 2025 | Completed final sign-off Nov 2025 | 2210 Stockton St | Wise Builders Inc | units 3056, 4056, 4055, 4004: kitchen and bath cabinets remove and replace. same location remodeling in kind.Details
units 3056, 4056, 4055, 4004: kitchen and bath cabinets remove and replace. same location remodeling in kind. | $160,000 |
| May 27, 2025 | In progress issued Jun 2025 | 2210 Stockton St | ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm systemDetails
ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system | ||
| May 27, 2025 | In progress issued Jun 2025 | 160 Bay St | ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm systemDetails
ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system | ||
| May 27, 2025 | In progress issued Jun 2025 | 165 North Point St | ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system as requested by sfdbi electrical inspector.Details
ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system as requested by sfdbi electrical inspector. | ||
| May 27, 2025 | In progress issued Jun 2025 | 2290 Stockton St | ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system as requested by dbi electrical inspector.Details
ref # pa 202403067223 administrative permit for record keeping of inspection for new fire alarm system as requested by dbi electrical inspector. | ||
| Jul 30, 2024 | Completed final sign-off Apr 2025 | 2290 Stockton St | Wise Builders Inc | units #3108, 3102, 2101: replace kitchen and bath cabinets and fixtures in same location. remodel in kind.Details
units #3108, 3102, 2101: replace kitchen and bath cabinets and fixtures in same location. remodel in kind. | $120,000 |
| Jul 30, 2024 | Completed final sign-off Apr 2025 | 165 North Point St | Wise Builders Inc | unit # 2155: replace kitchen and bath cabinets and fixtures in same locations. remodel in kind.Details
unit # 2155: replace kitchen and bath cabinets and fixtures in same locations. remodel in kind. | $40,000 |
| Apr 4, 2024 | Completed final sign-off Jul 2025 | 165 North Point St | Cm Electric | building c: fire alarm life safety system improvements motivated by sffd 2016 ordinance 163-16 + sf fire code section 1103.7.6.1 to achieve complaint occupation notification within sleeping areas. replace 86 existing smoke detectors.Details
building c: fire alarm life safety system improvements motivated by sffd 2016 ordinance 163-16 + sf fire code section 1103.7.6.1 to achieve complaint occupation notification within sleeping areas. replace 86 existing smoke detectors. | $20,000 |
| Jan 17, 2024 | Completed final sign-off Jul 2024 | 160 Bay St | Wise Builders Inc | unit's 2007,3004,3006, & 4012; replace kitchen and bahr cabinets, countertop and fixtures in same location. (in-kind remodel)Details
unit's 2007,3004,3006, & 4012; replace kitchen and bahr cabinets, countertop and fixtures in same location. (in-kind remodel) | $120,000 |
| Nov 10, 2022 | Completed final sign-off Jul 2023 | 165 North Point St | Wise Builders Inc | unit's 3150 and 3151: kitchen and bathroom repairs- electrical and plumbing fixtures in same locations. remove and replace cabinets and countertop in same location in kind.Details
unit's 3150 and 3151: kitchen and bathroom repairs- electrical and plumbing fixtures in same locations. remove and replace cabinets and countertop in same location in kind. | $48,000 |
| Nov 8, 2022 | Completed final sign-off Jul 2023 | 165 North Point St | Wise Builders Inc | unit 3159: one kitchen and bath. remoe and replace electrical and plumbing fixtures in same location. remove replace cabinets contertop in same location/kind. no wall changes.Details
unit 3159: one kitchen and bath. remoe and replace electrical and plumbing fixtures in same location. remove replace cabinets contertop in same location/kind. no wall changes. | $25,000 |
| Oct 31, 2022 | Completed final sign-off Jul 2023 | 165 North Point St | Wise Builders Inc | #4153: kitchen and bathroom: r&r electrial and plumbing fixtures in same location. r&r cabinets and counter tops in same location. in kind.Details
#4153: kitchen and bathroom: r&r electrial and plumbing fixtures in same location. r&r cabinets and counter tops in same location. in kind. | $25,000 |
| Dec 10, 2021 | Completed final sign-off Jun 2022 | 160 Bay St | Wise Builders Inc | unit 2008: kitchen and bath remodel to include: remove and replace cabinets with countertop, plumbing and electrical fixtures in the same location in existing apartment.Details
unit 2008: kitchen and bath remodel to include: remove and replace cabinets with countertop, plumbing and electrical fixtures in the same location in existing apartment. | $25,000 |
| Dec 9, 2021 | Completed final sign-off May 2022 | 165 North Point St | Wise Builders Inc | unit 3162: one kitchen and one bath remodel to include: remove and replace cabinets with countertop, plumbing and electrical fixtures in same location in existing apartment unit.Details
unit 3162: one kitchen and one bath remodel to include: remove and replace cabinets with countertop, plumbing and electrical fixtures in same location in existing apartment unit. | $25,000 |
| Dec 7, 2021 | Completed final sign-off May 2022 | 160 Bay St | Wise Builders Inc | unit# 2001: kitchen and bath remodeliing to include: remove and replace cabinets with countertop, plumbing, and electrical fixtures in same location in existing apartment unit.Details
unit# 2001: kitchen and bath remodeliing to include: remove and replace cabinets with countertop, plumbing, and electrical fixtures in same location in existing apartment unit. | $25,000 |
| Nov 20, 2020 | Completed final sign-off Dec 2023 | 2210 Stockton St | Saarman Construction,Ltd. | revision to 201812219004. changes are are windows and liding lass doors including showing operability directions and adding safety glazing, and additional interior gypsum wallboard removal at building c. also to document the split of original permit into 3 permits. this permit is for building c,Details
revision to 201812219004. changes are are windows and liding lass doors including showing operability directions and adding safety glazing, and additional interior gypsum wallboard removal at building c. also to document the split of original permit into 3 permits. this permit is for building c, | |
| Oct 14, 2020 | Expired or cancelled withdrawn Nov 2020 | 2210 Stockton St | Saarman Construction,Ltd. | revision to 201812219004. administrative permit to separate orig into 3 permits for 3 buildings which will share the plans of the original permit. this is for building c.Details
revision to 201812219004. administrative permit to separate orig into 3 permits for 3 buildings which will share the plans of the original permit. this is for building c. | |
| Aug 21, 2020 | Completed final sign-off Mar 2021 | 165 North Point St | Wise Builders Inc | apartment #2153#4157 and #4159: 3 kitchen and 3 bath remodel to include, remove & replace cabinets with counter top.plumbing fixtures, electrical fixtures in same location in apartment units. no change in walls & openings layout.Details
apartment #2153#4157 and #4159: 3 kitchen and 3 bath remodel to include, remove & replace cabinets with counter top.plumbing fixtures, electrical fixtures in same location in apartment units. no change in walls & openings layout. | $75,000 |
| Dec 19, 2019 | Never finaled issued Dec 2019, no final | 165 North Point St | street spaceDetails
street space | ||
| Nov 28, 2018 | Completed final sign-off Jun 2019 | 2210 Stockton St | building c: upgrade to the stairwell guardrails by an addition of infill panels to 8 stair enclosure.Details
building c: upgrade to the stairwell guardrails by an addition of infill panels to 8 stair enclosure. | $25,000 | |
| Sep 18, 2018 | Never finaled issued Sep 2018, no final | 160 Bay St | street spaceDetails
street space | ||
| Sep 18, 2018 | Completed final sign-off Nov 2018 | 160 Bay St | Regency General Contractors Inc | #4010: remodel 1 kitche n7 bath in kind. kitchen lighting min. 50% wattage. high effic. bathroom light controlled or sensor. main light high effic. no change to exhaust. no change to doors and windows.Details
#4010: remodel 1 kitche n7 bath in kind. kitchen lighting min. 50% wattage. high effic. bathroom light controlled or sensor. main light high effic. no change to exhaust. no change to doors and windows. | $20,000 |
| Jun 20, 2018 | Completed final sign-off Aug 2018 | 2290 Stockton St | Regency General Contractors Inc | remodel (1) kitchen and (1) bath in-kind in unit (3106). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficency controlled or manual-on sensor. main light high efficency. no change to exhaust system. no change in doors and windows and wall layout.Details
remodel (1) kitchen and (1) bath in-kind in unit (3106). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficency controlled or manual-on sensor. main light high efficency. no change to exhaust system. no change in doors and windows and wall layout. | $20,000 |
| Apr 2, 2018 | Completed final sign-off May 2018 | 160 Bay St | Regency General Contractors Inc | unit # 2004: remodel (1) kitchen & bath in kind in unit # 2004. kitchen lighting min. 50% wattage. high efficiency bath ligtht controlled or manual sensor. main light high efficiency. no change to exhaust. no chnage on doors or windows. n/a maherDetails
unit # 2004: remodel (1) kitchen & bath in kind in unit # 2004. kitchen lighting min. 50% wattage. high efficiency bath ligtht controlled or manual sensor. main light high efficiency. no change to exhaust. no chnage on doors or windows. n/a maher | $20,000 |
| Jan 9, 2018 | Completed final sign-off Mar 2018 | 2210 Stockton St | Regency General Contractors Inc | apt 4061: remodel kitchen & bathroom in-kind unit 2210-4061: kitchen lighting min 50% voltage h.e. bath light, controll on manual sensor. no hcange to exhaust fans, no change to doors & windows.Details
apt 4061: remodel kitchen & bathroom in-kind unit 2210-4061: kitchen lighting min 50% voltage h.e. bath light, controll on manual sensor. no hcange to exhaust fans, no change to doors & windows. | $20,000 |
| Nov 30, 2017 | Never finaled issued Nov 2017, no final | 2290 Stockton St | street space permit - renewal of permit #m848587Details
street space permit - renewal of permit #m848587 | ||
| Nov 2, 2017 | Completed final sign-off Apr 2018 | 165 North Point St | Regency General Contractors Inc | apt 2154: each unit: remodel 1 bathroom & 1 kitchen; kitchen lights are h.e. bathroom lighting. kitchen on manual, bathroom on sensor, no open walls or ceilings. no change to doors or windows & wall layouts.Details
apt 2154: each unit: remodel 1 bathroom & 1 kitchen; kitchen lights are h.e. bathroom lighting. kitchen on manual, bathroom on sensor, no open walls or ceilings. no change to doors or windows & wall layouts. | $20,000 |
| Sep 18, 2017 | Completed final sign-off Dec 2017 | 2290 Stockton St | Regency General Contractors Inc | #2100- remodel (1) kitchen (1) bath in kind, kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on doors and windows or walls. n/a ordinance #155-13Details
#2100- remodel (1) kitchen (1) bath in kind, kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on doors and windows or walls. n/a ordinance #155-13 | $20,000 |
| Aug 14, 2017 | Completed final sign-off Nov 2017 | 2290 Stockton St | Regency General Contractors Inc | remodel (1) kitchen (1) bath in kind in the follwoing unit 3104. kitchen lighting min 50% wattage high efficacy. bathroom light ligh efficacy controlled or manuel or sensor main light high efficacy. no change to exhaust system no change on doors and windows or walls.Details
remodel (1) kitchen (1) bath in kind in the follwoing unit 3104. kitchen lighting min 50% wattage high efficacy. bathroom light ligh efficacy controlled or manuel or sensor main light high efficacy. no change to exhaust system no change on doors and windows or walls. | $34,000 |
| Jun 19, 2017 | Completed final sign-off Sep 2017 | 2210 Stockton St | Regency General Contractors Inc | remodel (1) kitchen, (1) bath in kind in the following unit (3060). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows.Details
remodel (1) kitchen, (1) bath in kind in the following unit (3060). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows. | $35,000 |
| Jun 19, 2017 | Completed final sign-off Sep 2017 | 2290 Stockton St | Regency General Contractors Inc | remodel (1) kitchen, (1) bath in kind in the following unit (4102). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows.Details
remodel (1) kitchen, (1) bath in kind in the following unit (4102). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows. | $35,000 |
| Apr 27, 2017 | Completed final sign-off Jun 2017 | 2210 Stockton St | Regency General Contractors Inc | remodel (1) kitchen, (1) bath in kind in the following unit (3061). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows.Details
remodel (1) kitchen, (1) bath in kind in the following unit (3061). kitchen lighting min. 50% wattage high efficacy, bathroom light high efficacy controlled or manual or sensor, main light high efficacy. no change to exhaust system. no change on door and windows. | $20,000 |
| Apr 13, 2017 | Never finaled issued Apr 2017, no final | 2210 Stockton St | Shaughnessy Roofing Inc | reroofingDetails
reroofing | $785,000 |
| Mar 21, 2017 | Completed final sign-off May 2017 | 2290 Stockton St | Regency General Contractors Inc | remodel (1) kitchen and (1) bath in kind. unit 3103. kitchen lighting min 50% watt high efficacy. bathroom light high efficacy controlled or manuel or sensor main light high efficacy. no change to exhaust system. no change to door and windows. no walls moved, removed, added or infilled. all existingDetails
remodel (1) kitchen and (1) bath in kind. unit 3103. kitchen lighting min 50% watt high efficacy. bathroom light high efficacy controlled or manuel or sensor main light high efficacy. no change to exhaust system. no change to door and windows. no walls moved, removed, added or infilled. all existing | $20,000 |
| Jan 12, 2017 | Completed final sign-off Feb 2017 | 160 Bay St | Regency General Contractors Inc | apt 4005: remodel (1) kitchen & (1) bathroom in-kind. kitchen lighting min 50% wattage h.e. bathroom light h.e. controlled or manual sensor, main light h.e. no change to exhaust system, no change to doors, windows or walls.Details
apt 4005: remodel (1) kitchen & (1) bathroom in-kind. kitchen lighting min 50% wattage h.e. bathroom light h.e. controlled or manual sensor, main light h.e. no change to exhaust system, no change to doors, windows or walls. | $20,000 |
| Nov 30, 2016 | Completed final sign-off Jan 2017 | 160 Bay St | Regency General Contractors Inc | apt 4007: remodel 1 kitchen & bathroom in-kind. kitchen lighting min 50% wattage h.e. bathroomlight h.e. controlled or manual or sensor, main light h.e. no change to (e) system, no change on doors and windows. no walls to be altered.Details
apt 4007: remodel 1 kitchen & bathroom in-kind. kitchen lighting min 50% wattage h.e. bathroomlight h.e. controlled or manual or sensor, main light h.e. no change to (e) system, no change on doors and windows. no walls to be altered. | $20,000 |
| Nov 2, 2016 | Completed final sign-off Dec 2016 | 2210 Stockton St | Regency General Contractors Inc | apt 4059: remodel kitchen & bathroom inkind. kitchen lighting min 50% wattage h.e.. bathroom light h.e. controlled or manual or sensor. main light h.e. no change to exhaust system. no change on doors or windows.Details
apt 4059: remodel kitchen & bathroom inkind. kitchen lighting min 50% wattage h.e.. bathroom light h.e. controlled or manual or sensor. main light h.e. no change to exhaust system. no change on doors or windows. | $20,000 |
| Aug 2, 2016 | Completed final sign-off Nov 2016 | 160 Bay St | Regency General Contractors Inc | remodel (2) kitchen and 2 bath in kind in the following units: (160-3011), (2290-4111), kitchen lighting min. 50% wattage high efficacy. vathroom lihgting high efficacy.Details
remodel (2) kitchen and 2 bath in kind in the following units: (160-3011), (2290-4111), kitchen lighting min. 50% wattage high efficacy. vathroom lihgting high efficacy. | $40,000 |
| Apr 19, 2016 | Completed final sign-off Aug 2016 | 160 Bay St | Regency General Contractors Inc | apt 4002: remodel 1 kitchen & 1 bathroom in-kind. kitchen lightingmin 50% wattage h.e, bathroom lighting h.e. controller or manual or sensor & main light h.e.. no change to exhaust sytem, no change in doors or windows. no walls or ceilings opened.Details
apt 4002: remodel 1 kitchen & 1 bathroom in-kind. kitchen lightingmin 50% wattage h.e, bathroom lighting h.e. controller or manual or sensor & main light h.e.. no change to exhaust sytem, no change in doors or windows. no walls or ceilings opened. | $20,000 |
| Jan 12, 2016 | Completed final sign-off Mar 2016 | 160 Bay St | Regency General Contractors Inc | apts 2003 & 3012: each unit: remodel kitchen & bathroom in-kind. kithcen lightingmin 50% wattage h.e., bathroomlighting h.e.controlled or manual or sensor & main light h.e.. no change to exhaust system, no change on doors and windows.Details
apts 2003 & 3012: each unit: remodel kitchen & bathroom in-kind. kithcen lightingmin 50% wattage h.e., bathroomlighting h.e.controlled or manual or sensor & main light h.e.. no change to exhaust system, no change on doors and windows. | $40,000 |
| Nov 18, 2015 | Completed final sign-off Feb 2016 | 160 Bay St | Regency General Contractors Inc | remodel 2 units kitchen & bath in-kind in the following units. @160 unit#4003 & @ 165 unit#3163. kitchen lighting min 50% wattage high efficacy. no change to exhaust system. no change to door & windows & wall layout. n/a for maher.Details
remodel 2 units kitchen & bath in-kind in the following units. @160 unit#4003 & @ 165 unit#3163. kitchen lighting min 50% wattage high efficacy. no change to exhaust system. no change to door & windows & wall layout. n/a for maher. | $40,000 |
| Oct 29, 2015 | Completed final sign-off Jan 2016 | 2210 Stockton St | Regency General Contractors Inc | 2210-4054 & 2290-4105: remodel (2 units): kitchen & bathroom in-kind. kitchen lighting min 50% wattage high efficency , bathrom lighting high efficiency or controlled manuel on sensor & main light h.e. no change to exhaust system, no change to doors, window openings or wall locations.Details
2210-4054 & 2290-4105: remodel (2 units): kitchen & bathroom in-kind. kitchen lighting min 50% wattage high efficency , bathrom lighting high efficiency or controlled manuel on sensor & main light h.e. no change to exhaust system, no change to doors, window openings or wall locations. | $40,000 |
| Sep 9, 2015 | Never finaled issued Sep 2015, no final | 2210 Stockton St | street space permitDetails
street space permit | ||
| Jul 31, 2015 | Never finaled issued Jul 2015, no final | 165 North Point St | street space permitDetails
street space permit | ||
| Jul 29, 2015 | Never finaled issued Jul 2015, no final | 2210 Stockton St | Richard Joseph Construction Inc | replace windows @ courtyard. existing courtyard windows are all aluminum single pane windows being replaced with double pane vinyl windows. approx. 400 nos. same size & locations. u factor not > .32; n/a maher ord. # 155-13Details
replace windows @ courtyard. existing courtyard windows are all aluminum single pane windows being replaced with double pane vinyl windows. approx. 400 nos. same size & locations. u factor not > .32; n/a maher ord. # 155-13 | $500,000 |
| Jul 15, 2015 | Completed final sign-off Sep 2015 | 2210 Stockton St | Regency General Contractors Inc | remodel 2 units, #4051 and #4057: kitchen and bath in kind. kitchen lighting, min 50% wattage high efficacy, bathroom lighting high efficacy or controlled manual on sensor and main light high efficacy. no change to exhaust system. no change to doors an windows opening and wall layout.Details
remodel 2 units, #4051 and #4057: kitchen and bath in kind. kitchen lighting, min 50% wattage high efficacy, bathroom lighting high efficacy or controlled manual on sensor and main light high efficacy. no change to exhaust system. no change to doors an windows opening and wall layout. | $40,000 |
| May 29, 2015 | Never finaled issued May 2015, no final | 2210 Stockton St | street spaceDetails
street space | ||
| May 8, 2015 | Completed final sign-off Nov 2015 | 160 Bay St | to obtain final inspection for work approved under pa201303061634.Details
to obtain final inspection for work approved under pa201303061634. | $5,000 | |
| Apr 24, 2015 | Completed final sign-off Jun 2015 | 2210 Stockton St | Regency General Contractors Inc | remodel (1 unit) kitchen & bath in kind each in the ff units: 2210-4058: kitchen lighting min 50% wattage high efficacy,bathrm lighting high efficacy or controlled by manual on sensor and main light, no change to exhaust system,no change to doors & windows opening, &wall layout.Details
remodel (1 unit) kitchen & bath in kind each in the ff units: 2210-4058: kitchen lighting min 50% wattage high efficacy,bathrm lighting high efficacy or controlled by manual on sensor and main light, no change to exhaust system,no change to doors & windows opening, &wall layout. | $20,000 |
| Apr 22, 2015 | Never finaled issued Apr 2015, no final | 165 North Point St | street spaceDetails
street space | ||
| Apr 22, 2015 | Never finaled issued Apr 2015, no final | 160 Bay St | street spaceDetails
street space | ||
| Mar 26, 2015 | Completed final sign-off May 2015 | 160 Bay St | Regency General Contractors Inc | remodel (1 unit) kitchen and bath in kiind in the following unit 4014. lighting to comply with cec. 150k. no change to exhaust system. no change to structural, doors and windows.Details
remodel (1 unit) kitchen and bath in kiind in the following unit 4014. lighting to comply with cec. 150k. no change to exhaust system. no change to structural, doors and windows. | $15,000 |
| Mar 4, 2015 | Expired or cancelled withdrawn May 2015 | 2210 Stockton St | Swinerton Builders | demo () roll down smoke door in type ib parking garge maher - not req'dDetails
demo () roll down smoke door in type ib parking garge maher - not req'd | $9,000 |
| Feb 26, 2015 | Never finaled issued Feb 2015, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Feb 25, 2015 | Never finaled issued Feb 2015, no final | 2290 Stockton St | street space permitDetails
street space permit | ||
| Jan 13, 2015 | Completed final sign-off May 2018 | 160 Bay St | Regency General Contractors Inc | remodel unit 317 kitchen & bath in kind. lighting to comply with cec 150k, no change to exhaust system, no change to structure, wall doors and windowsDetails
remodel unit 317 kitchen & bath in kind. lighting to comply with cec 150k, no change to exhaust system, no change to structure, wall doors and windows | $20,000 |
| Dec 31, 2014 | Expired or cancelled withdrawn Jan 2015 | 2210 Stockton St | Pacific Coast Trane Service Co. | replacement of 8 fire dampers at lower garage exhaust shaft point of connection ref 201409267479 maher not reqDetails
replacement of 8 fire dampers at lower garage exhaust shaft point of connection ref 201409267479 maher not req | $50,000 |
| Dec 30, 2014 | Never finaled issued Apr 2015, no final | 2290 Stockton St | Sabah International Incorporated | fire alarm system replacement on a one-for-one basis per interim facp replacement guidelines. maher ordinance is not required.Details
fire alarm system replacement on a one-for-one basis per interim facp replacement guidelines. maher ordinance is not required. | $72,500 |
| Nov 18, 2014 | Never finaled issued Nov 2014, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Oct 6, 2014 | Completed final sign-off Apr 2015 | 160 Bay St | Regency General Contractors Inc | remodel (3) units kitchen and bath in kind in the following units: (160-423; (165-218); 2210-204) lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors and windows.Details
remodel (3) units kitchen and bath in kind in the following units: (160-423; (165-218); 2210-204) lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors and windows. | $45,000 |
| Sep 26, 2014 | Completed final sign-off Dec 2015 | 2210 Stockton St | Pacific Coast Trane Service Co. | bldg a&b: removal of (8) exhaust fans on roof, install 8 new exhaust fans, vfds, and exhaust plenums in garage, ductwork modification at new garage poc and roof vents; maher n/aDetails
bldg a&b: removal of (8) exhaust fans on roof, install 8 new exhaust fans, vfds, and exhaust plenums in garage, ductwork modification at new garage poc and roof vents; maher n/a | $150,000 |
| Aug 21, 2014 | Never finaled issued Aug 2014, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Aug 20, 2014 | Never finaled issued Aug 2014, no final | 2290 Stockton St | street spaceDetails
street space | ||
| Aug 4, 2014 | Completed final sign-off Oct 2014 | 2210 Stockton St | Regency General Contractors Inc | remodel(5 units) kitchen & bath in-kind in the following units: 2210-405, 2210-303, 2210-205, 2290-307, 160-226. lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors & windows.Details
remodel(5 units) kitchen & bath in-kind in the following units: 2210-405, 2210-303, 2210-205, 2290-307, 160-226. lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors & windows. | $75,000 |
| Aug 4, 2014 | Completed final sign-off Oct 2014 | 165 North Point St | Regency General Contractors Inc | remodel(5 units) kitchen & bath in-kind in the following units: 165-427, 165-315, 165-226, 165-224, 2290=210. lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors & windows. compliance with maher ordinance no 155-13 not required.Details
remodel(5 units) kitchen & bath in-kind in the following units: 165-427, 165-315, 165-226, 165-224, 2290=210. lighting to comply with cec 150k. no change to exhaust system. no change to structural, doors & windows. compliance with maher ordinance no 155-13 not required. | $75,000 |
| Mar 13, 2014 | Never finaled issued Mar 2014, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Feb 14, 2014 | Never finaled issued Feb 2014, no final | 2290 Stockton St | street spaceDetails
street space | ||
| Feb 14, 2014 | Completed final sign-off Nov 2014 | 2210 Stockton St | courtyard c - revision to pa# 201303061632 temporary opening at structural slab for debris removal, slab will be replaced in kind. compliance with ordinance #155-13 not required.Details
courtyard c - revision to pa# 201303061632 temporary opening at structural slab for debris removal, slab will be replaced in kind. compliance with ordinance #155-13 not required. | $15,000 | |
| Feb 14, 2014 | Completed final sign-off May 2014 | 2290 Stockton St | Regency General Contractors Inc | unit 209 - kitchen and bath remodel ; to comply with cec150(k) 8 & 10; mno change to exhaust system, structural, doors and windows, (e) wall to remain as its.Details
unit 209 - kitchen and bath remodel ; to comply with cec150(k) 8 & 10; mno change to exhaust system, structural, doors and windows, (e) wall to remain as its. | $15,000 |
| Feb 14, 2014 | Completed final sign-off May 2014 | 2290 Stockton St | Regency General Contractors Inc | unit 301 - kitchen and bath remodel; lighting to comply with cec150(k) 8 & 10; no change ot exhaust system, stiurctural, door window, (e) wall to remain as it is.Details
unit 301 - kitchen and bath remodel; lighting to comply with cec150(k) 8 & 10; no change ot exhaust system, stiurctural, door window, (e) wall to remain as it is. | $15,000 |
| Jan 31, 2014 | Never finaled issued Jan 2014, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Jan 3, 2014 | Completed final sign-off Apr 2014 | 165 North Point St | Regency General Contractors Inc | unit #321: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain.Details
unit #321: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain. | $30,000 |
| Jan 3, 2014 | Completed final sign-off Apr 2014 | 160 Bay St | Regency General Contractors Inc | unit #104: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain.Details
unit #104: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain. | $30,000 |
| Jan 3, 2014 | Completed final sign-off Apr 2014 | 165 North Point St | Regency General Contractors Inc | unit #220: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain.Details
unit #220: remodel kitchen, 1 bath in-kind, lighting to comply w/cec 150k 8-10, no change to exhaust system, no change to structural, doors & windows, all (e) wall to remain. | $30,000 |
| Nov 14, 2013 | Completed final sign-off Jan 2014 | 2210 Stockton St | Regency General Contractors Inc | remodel kitchen & bath in following units (2210-#207), (160- #105) and (2290-#414), lighting to comply with cec150k, 8-10, no change to exhaust system, no changes to structural doors and windows (3 bathrooms and 3 kitchen total)Details
remodel kitchen & bath in following units (2210-#207), (160- #105) and (2290-#414), lighting to comply with cec150k, 8-10, no change to exhaust system, no changes to structural doors and windows (3 bathrooms and 3 kitchen total) | $90,000 |
| Nov 7, 2013 | Completed final sign-off Jan 2014 | 165 North Point St | Regency General Contractors Inc | #428- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain.Details
#428- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain. | $30,000 |
| Nov 7, 2013 | Completed final sign-off Jan 2014 | 2290 Stockton St | Regency General Contractors Inc | #201- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain.Details
#201- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain. | $30,000 |
| Nov 7, 2013 | Completed final sign-off Jan 2014 | 165 North Point St | Regency General Contractors Inc | #165- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain.Details
#165- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain. | $30,000 |
| Nov 7, 2013 | Completed final sign-off Jan 2014 | 2290 Stockton St | Regency General Contractors Inc | #207- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain.Details
#207- remodel kitchen & bath. lighting to comply with cec150k 8-10, no change to exhaust system, no change to structural, doors & windows. all (e) wall to remain. | $30,000 |
| Oct 21, 2013 | Completed final sign-off Jul 2014 | 2210 Stockton St | Sabah International Incorporated | f.a system replacement on a one -for-one basis per the sffd interim replacement guidelines. to compliance with ordinance no. 155-13 not required. excavation <50 cu.yd.Details
f.a system replacement on a one -for-one basis per the sffd interim replacement guidelines. to compliance with ordinance no. 155-13 not required. excavation <50 cu.yd. | $50,700 |
| Aug 2, 2013 | Never finaled issued Aug 2013, no final | 2210 Stockton St | street space permit (201303061632)Details
street space permit (201303061632) | ||
| Jul 30, 2013 | Completed final sign-off Oct 2013 | 160 Bay St | Regency General Contractors Inc | unit 318 remodel kitchen & bath in kind (160-#318), lighting to comply with cec 150k, no change to exhaust system, no change to structural, doors & windowsDetails
unit 318 remodel kitchen & bath in kind (160-#318), lighting to comply with cec 150k, no change to exhaust system, no change to structural, doors & windows | $15,000 |
| Jul 30, 2013 | Completed final sign-off Oct 2013 | 160 Bay St | Regency General Contractors Inc | remodel kitchen & bath in kind (160 - 420), lighting to comply with cec 150k, no change to exhaust system, no change to structural, door & windowsDetails
remodel kitchen & bath in kind (160 - 420), lighting to comply with cec 150k, no change to exhaust system, no change to structural, door & windows | $15,000 |
| Jul 30, 2013 | Completed final sign-off Oct 2013 | 2210 Stockton St | Regency General Contractors Inc | unit 203 remodel kitchen & bath in kind (2210-#303), lighting to comple w cec 150k. no change to exhaust system , no change to structural, doors & windowsDetails
unit 203 remodel kitchen & bath in kind (2210-#303), lighting to comple w cec 150k. no change to exhaust system , no change to structural, doors & windows | $15,000 |
| Jul 30, 2013 | Completed final sign-off Oct 2013 | 2210 Stockton St | Regency General Contractors Inc | unit 214 - remodel kitchen & bath in kind: (2210 - #214) lighting to comply with cec 150k, nochange to exhaust system, no change to structural, door & windows.Details
unit 214 - remodel kitchen & bath in kind: (2210 - #214) lighting to comply with cec 150k, nochange to exhaust system, no change to structural, door & windows. | $15,000 |
| Jul 23, 2013 | Completed final sign-off Nov 2014 | 2210 Stockton St | to obtain final inspection for work approved under pa#201111289609. all work is completeDetails
to obtain final inspection for work approved under pa#201111289609. all work is complete | ||
| Jul 22, 2013 | Completed final sign-off Nov 2014 | 2210 Stockton St | bldg c - revision to pa #2013.0306.1632 & 2011.1128.9609: revise pool steps & provide pool lift. new fence & landscape to existing swimming pool.Details
bldg c - revision to pa #2013.0306.1632 & 2011.1128.9609: revise pool steps & provide pool lift. new fence & landscape to existing swimming pool. | $20,000 | |
| May 31, 2013 | Completed final sign-off Aug 2013 | 160 Bay St | Regency General Contractors Inc | remodel 4 units kithcne & bath in kind in the following: (160 # 319 ) (160 # 325) (165 # 104) & (165 # 420) lighting to comply with cec 150k, no change to exhaust system, no change to structural doors & windows.Details
remodel 4 units kithcne & bath in kind in the following: (160 # 319 ) (160 # 325) (165 # 104) & (165 # 420) lighting to comply with cec 150k, no change to exhaust system, no change to structural doors & windows. | $60,000 |
| Mar 25, 2013 | Never finaled issued Mar 2013, no final | 2210 Stockton St | revision to pa# 2012-0213-4091, replace metal mech walls not new concrete infills.Details
revision to pa# 2012-0213-4091, replace metal mech walls not new concrete infills. | $3,500 | |
| Mar 19, 2013 | Completed final sign-off Jul 2013 | 2290 Stockton St | Regency General Contractors Inc | remodel kitchen & bath in kind in the following 5 units: 2290-#411, #102, 165-#105, 2210-#221, #202. lighting to comply with cec 150k. no change to exhaust system, no changes on structural doors & windows.Details
remodel kitchen & bath in kind in the following 5 units: 2290-#411, #102, 165-#105, 2210-#221, #202. lighting to comply with cec 150k. no change to exhaust system, no changes on structural doors & windows. | $75,000 |
| Mar 6, 2013 | Never finaled issued Apr 2013, no final | 160 Bay St | Swinerton Builders | replacing the waterproofing at the courtyard "a" due to water infiltration at concrete slab causing structural damage. install new water featuresDetails
replacing the waterproofing at the courtyard "a" due to water infiltration at concrete slab causing structural damage. install new water features | $30,000 |
| Mar 6, 2013 | Completed final sign-off Nov 2014 | 2210 Stockton St | Swinerton Builders | replacing the waterproofing at the courtyard "c" due to water infiltration at concrete slab causing structural damage. install new water featuresDetails
replacing the waterproofing at the courtyard "c" due to water infiltration at concrete slab causing structural damage. install new water features | $30,000 |
| Jan 16, 2013 | Completed final sign-off Feb 2013 | 2290 Stockton St | Regency General Contractors Inc | remodel (5) kitchens & (5) bathrooms in kind in the folowing units: 165 north point units: 325, 222; 2290 stocktock units: 306, 406, 403; no structural change. no doors and no windows. lighting to comply to cec 8, 10 150k no change to exhaust system.Details
remodel (5) kitchens & (5) bathrooms in kind in the folowing units: 165 north point units: 325, 222; 2290 stocktock units: 306, 406, 403; no structural change. no doors and no windows. lighting to comply to cec 8, 10 150k no change to exhaust system. | $75,000 |
| Dec 13, 2012 | Completed final sign-off Feb 2013 | 2210 Stockton St | Regency General Contractors Inc | remodel 5 kitchen & 5 bathrooms in kind in the following units: 2210 stockton st., units 314, 402, 160 bay st., units 221, 320, 2290 stockton st., unit 402. no structural change, no doors, no windows, no change to exhaust system. lighting to comply with cec 150(k)Details
remodel 5 kitchen & 5 bathrooms in kind in the following units: 2210 stockton st., units 314, 402, 160 bay st., units 221, 320, 2290 stockton st., unit 402. no structural change, no doors, no windows, no change to exhaust system. lighting to comply with cec 150(k) | $75,000 |
| Nov 13, 2012 | Completed final sign-off Jan 2013 | 165 North Point St | Regency General Contractors Inc | remodel 5 kitchens, 5 bathrooms in kind in the following unnits. 165 north point # 419, 421. 422. 316, 219. replace existing in same location. lighting to comply with cec 150(k). no change to exhaust system.Details
remodel 5 kitchens, 5 bathrooms in kind in the following unnits. 165 north point # 419, 421. 422. 316, 219. replace existing in same location. lighting to comply with cec 150(k). no change to exhaust system. | $75,000 |
| Sep 24, 2012 | Completed final sign-off Nov 2012 | 2210 Stockton St | Regency General Contractors Inc | 2201 stockton #404, #206, 2290 stockton #305, #204: remodel 4 kitchens & baths in kind. no structural work, lighting to comply cec150(k)8,10. no change to exhaust system. kitchen 8x7, bath 5x7Details
2201 stockton #404, #206, 2290 stockton #305, #204: remodel 4 kitchens & baths in kind. no structural work, lighting to comply cec150(k)8,10. no change to exhaust system. kitchen 8x7, bath 5x7 | $60,000 |
| Sep 24, 2012 | Completed final sign-off Nov 2012 | 160 Bay St | Regency General Contractors Inc | #218: remodel 1 kitchen, 1 bath. no structural work, lighting to comply cec150(k)8, no change to exhaust system.Details
#218: remodel 1 kitchen, 1 bath. no structural work, lighting to comply cec150(k)8, no change to exhaust system. | $15,000 |
| Sep 14, 2012 | Never finaled issued Nov 2012, no final | 2210 Stockton St | erect an electric wall single faced replacement signDetails
erect an electric wall single faced replacement sign | $2,000 | |
| Aug 9, 2012 | Completed final sign-off Sep 2012 | 165 North Point St | Regency General Contractors Inc | remodel 4 kitchen & bath in kind in the following units. 165 north point nit#417,322,326. 160 bay st unit#425. no structural work. lighting to comply cec 150 k. no change to exhaust system.Details
remodel 4 kitchen & bath in kind in the following units. 165 north point nit#417,322,326. 160 bay st unit#425. no structural work. lighting to comply cec 150 k. no change to exhaust system. | $75,000 |
| Jul 17, 2012 | Completed final sign-off Sep 2012 | 2290 Stockton St | Regency General Contractors Inc | remodel (5) kitchens, (2) baths in kind in the following units: 160 bay street: units 213, 220; 165 north point: unit 416; 2290 stockton street: units 202, 203; (kitchen - 170 sq. ft. & bath: 100 sq. ft); lighting to comply with c & c 150 k. no change to exhaust system.Details
remodel (5) kitchens, (2) baths in kind in the following units: 160 bay street: units 213, 220; 165 north point: unit 416; 2290 stockton street: units 202, 203; (kitchen - 170 sq. ft. & bath: 100 sq. ft); lighting to comply with c & c 150 k. no change to exhaust system. | $75,000 |
| Jun 8, 2012 | Completed final sign-off Aug 2012 | 2210 Stockton St | Regency General Contractors Inc | remodel 5 kitchen and bath in kind in the following units: 2290 stockton st. unit #208, 214, 412. 2210 stockton st. unit #302, 309. lighting to comply with cec 150(k). no change to exhaust sytem.Details
remodel 5 kitchen and bath in kind in the following units: 2290 stockton st. unit #208, 214, 412. 2210 stockton st. unit #302, 309. lighting to comply with cec 150(k). no change to exhaust sytem. | $75,000 |
| Apr 24, 2012 | Completed final sign-off Jun 2012 | 2210 Stockton St | Regency General Contractors Inc | remodel 5 kitchens and bath in kind in the following units #2210 stockton unit #310,210,212,201,102, non structuralDetails
remodel 5 kitchens and bath in kind in the following units #2210 stockton unit #310,210,212,201,102, non structural | $75,000 |
| Apr 9, 2012 | Completed final sign-off May 2012 | 2290 Stockton St | Regency General Contractors Inc | work in unit 409: remodel 1 kitchen and bathroom in kind at unit #409, no wall relocation. lighting to comply with cec150(k)8 for kitchen remodel and cec150(k)10 for bathroom remodel.Details
work in unit 409: remodel 1 kitchen and bathroom in kind at unit #409, no wall relocation. lighting to comply with cec150(k)8 for kitchen remodel and cec150(k)10 for bathroom remodel. | $15,000 |
| Apr 9, 2012 | Completed final sign-off May 2012 | 165 North Point St | Regency General Contractors Inc | remodel 1 kitchen & bathroom in kind at each of the unit #324, 418 & 424. no wall relocation. lighting to comply with cec 150(k)8 for kitchen and cec 150(k)10 for bathroom remodel.Details
remodel 1 kitchen & bathroom in kind at each of the unit #324, 418 & 424. no wall relocation. lighting to comply with cec 150(k)8 for kitchen and cec 150(k)10 for bathroom remodel. | $45,000 |
| Mar 14, 2012 | Completed final sign-off Apr 2012 | 160 Bay St | Regency General Contractors Inc | remodel 5 kitchen and bath in kind in the following units: 160-426,160-326,160-315,160-324,160-223 lighting to comply with cec 150k no changes to exhaust sytemsDetails
remodel 5 kitchen and bath in kind in the following units: 160-426,160-326,160-315,160-324,160-223 lighting to comply with cec 150k no changes to exhaust sytems | $75,000 |
| Feb 13, 2012 | Never finaled issued Feb 2012, no final | 2210 Stockton St | replacing of gates, wall railings, and balcony railings. new concrete in fill walls and metal dividers in between the top of existing concrete wall and window slabs. new metal lid ceilings at gate enclosures.Details
replacing of gates, wall railings, and balcony railings. new concrete in fill walls and metal dividers in between the top of existing concrete wall and window slabs. new metal lid ceilings at gate enclosures. | $50,000 | |
| Feb 9, 2012 | Never finaled issued Feb 2012, no final | 2210 Stockton St | street space permitDetails
street space permit | ||
| Jan 17, 2012 | Completed final sign-off Mar 2012 | 2290 Stockton St | Regency General Contractors Inc | remodel (4) kitchens and baths in kind. studio units in the following units: 160-327, 165-216, 2290-211, 2290-308. lighting to comply with cec 150k. no change to exhaust system.Details
remodel (4) kitchens and baths in kind. studio units in the following units: 160-327, 165-216, 2290-211, 2290-308. lighting to comply with cec 150k. no change to exhaust system. | $60,000 |
| Nov 28, 2011 | Expired or cancelled expired Nov 2014 | 2210 Stockton St | repair work at extg pool. new membrane and liner. replace/repair drain lines and new concrete. decking at pool.Details
repair work at extg pool. new membrane and liner. replace/repair drain lines and new concrete. decking at pool. | $25,000 | |
| Nov 9, 2011 | Completed final sign-off May 2012 | 2210 Stockton St | smoke tower improvements at roof level. not visible from the street. reference drawing #201009211312Details
smoke tower improvements at roof level. not visible from the street. reference drawing #201009211312 | $15,000 | |
| Apr 11, 2011 | Never finaled issued Apr 2011, no final | 165 North Point St | street spaceDetails
street space | ||
| Jan 26, 2011 | Never finaled issued Jan 2011, no final | 2290 Stockton St | Tyco Integrated Security | due to the malfuntion of the audio card at the exist control panel. adt will install new power supply next to the dialer in the garage area and tie notificaion wiring to the power supply. as built plans are required.Details
due to the malfuntion of the audio card at the exist control panel. adt will install new power supply next to the dialer in the garage area and tie notificaion wiring to the power supply. as built plans are required. | $2,700 |
| Jan 26, 2011 | Never finaled issued Jan 2011, no final | 2210 Stockton St | Tyco Integrated Security | due to the malfuntion of the audio card at the exist control panel. adt will install new power supply next to the dialer in the garage area and tie notificaion wiring to the power supply. as built are required.Details
due to the malfuntion of the audio card at the exist control panel. adt will install new power supply next to the dialer in the garage area and tie notificaion wiring to the power supply. as built are required. | $2,700 |
| Nov 17, 2010 | Never finaled issued Nov 2010, no final | 165 North Point St | street spaceDetails
street space | ||
| Nov 3, 2010 | Never finaled issued Nov 2010, no final | 2210 Stockton St | street spaceDetails
street space | ||
| Oct 9, 2008 | Never finaled issued Oct 2008, no final | 165 North Point St | street space & sidewalk permit only.Details
street space & sidewalk permit only. | ||
| Oct 9, 2008 | Never finaled issued Oct 2008, no final | 160 Bay St | street space & sidewalk permit only.Details
street space & sidewalk permit only. |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Regency General Contractors Inc (55), Wise Builders Inc (12), Swinerton Builders (3), Pacific Coast Trane Service Co. (2), Saarman Construction,Ltd. (2), Sabah International Incorporated (2), Tyco Integrated Security (2), Allied Fire Protection, Cm Electric, Richard Joseph Construction Inc, Shaughnessy Roofing Inc
- Architects
- John Mcnulty (2)
- Engineers
- Carolyn Searls, Lars Fagerstrom, Stephen Harris
- Designers
- Sven Fagerstrom
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.