Robert Okano
- License
- S4976
- Structural engineer
- About the Board for Professional Engineers, Land Surveyors, and Geologists
- Look up S4976 at the Board for Professional Engineers
- Listed as
- engineer
- On San Francisco permits
- Feb 2022 to Feb 2022
1 permit since 2000 (engineer on 1 permit): 1 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- Cupertino Electric Inc.
- Engineers
- Emmanuel Memdo
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 0
- Commercial 0
- Other or unknown 1
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 17, 2022 | Completed final sign-off Aug 2023 | 2860 16th St | Cupertino Electric Inc. | installation of: single & dual port level 3 ev chargers, main switchboard & auxiliary power, power distribution system, sub metering system, lighting & control systems, grounding system, & conduit for security system, access & telecom systems.Details
installation of: single & dual port level 3 ev chargers, main switchboard & auxiliary power, power distribution system, sub metering system, lighting & control systems, grounding system, & conduit for security system, access & telecom systems. | $1,580,530 |