Daniel Marketta
- Listed as
- engineer
- Firm
- Core States Group
- Based in
- Ontario
- On San Francisco permits
- Feb 2026 to Sep 2026
5 permits since 2000 (engineer on 5 permits): 5 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 10, 2026 | In progress filed Sep 2026, not yet issued | 1483 Mason St | Corestates Construction Services Inc | installatoin of 4 artemis plugzio 48a level 2 ev chargers. evse to be shared by resident and staff ev drivers in ground level covered garage.Details
installatoin of 4 artemis plugzio 48a level 2 ev chargers. evse to be shared by resident and staff ev drivers in ground level covered garage. | $48,408 |
| Apr 23, 2026 | In progress issued Sep 2026 | 3590 20th St | Corestates Construction Services Inc | level 2 ev chargers, installation of nine (9) evercharge.ev002 ev chargers ("evse") to be assigned to staff / resident ev drivers in assigned parking areas.Details
level 2 ev chargers, installation of nine (9) evercharge.ev002 ev chargers ("evse") to be assigned to staff / resident ev drivers in assigned parking areas. | $62,300 |
| Apr 21, 2026 | In progress issued Aug 2026 | 1880 Steiner St | Corestates Construction Services Inc | level 2 ev chargers: installation of (5) tesla universal wall connectors ("evse") to be assigned to residents and/or staff. ev drivers in private parking areas of underground parking garage.Details
level 2 ev chargers: installation of (5) tesla universal wall connectors ("evse") to be assigned to residents and/or staff. ev drivers in private parking areas of underground parking garage. | $45,521 |
| Feb 26, 2026 | In progress filed Feb 2026, not yet issued | 1301 La Playa | Corestates Construction Services Inc | installation of level 2 evcs, 9 tesla universal wall connector 48a ev chargers ("evse") to be assigned to staff/ resident ev drivers in assigned parking areas.Details
installation of level 2 evcs, 9 tesla universal wall connector 48a ev chargers ("evse") to be assigned to staff/ resident ev drivers in assigned parking areas. | $69,739 |
| Feb 19, 2026 | In progress filed Feb 2026, not yet issued | 81 Lansing St | Corestates Construction Services Inc | the installation of nine (9) evercharge ev002 48a wifi enabled ev chargers in parking area.Details
the installation of nine (9) evercharge ev002 48a wifi enabled ev chargers in parking area. | $87,067 |