Sue Marzuola
- Listed as
- architect
- Firm
- Siegel & Strain Arch.
- Based in
- Emeryville
- On San Francisco permits
- Nov 2006 to Jul 2012
7 permits since 2000 (architect on 7 permits): 7 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 12, 2012 | Completed final sign-off Sep 2012 | 2120 Broadway | Plant Construction Company Lp | subdivide existing library stack room to provide two offices & a reading room in stanwood hall. mechanical, electrical & fire sprinkler work under separate permit.Details
subdivide existing library stack room to provide two offices & a reading room in stanwood hall. mechanical, electrical & fire sprinkler work under separate permit. | $100,000 |
| Jun 24, 2011 | Completed final sign-off Dec 2011 | 2129 Vallejo St | San Francisco Commercial Builders Inc | remove & replace theatrical rigging above stage & portion of gym on 3rd floor. electrical work to be under separate permit.Details
remove & replace theatrical rigging above stage & portion of gym on 3rd floor. electrical work to be under separate permit. | $50,000 |
| Jul 14, 2010 | Completed final sign-off Jan 2011 | 2120 Broadway | Plant Construction Company Lp | revision to pa# 2010.04.12.0036. substitute hand dug piers for micropiles shown as delta 2, dated july 13, 2010. hand dug piers per plan.Details
revision to pa# 2010.04.12.0036. substitute hand dug piers for micropiles shown as delta 2, dated july 13, 2010. hand dug piers per plan. | $5,000 |
| Apr 12, 2010 | Completed final sign-off Jan 2011 | 2120 Broadway | Plant Construction Co, Lp | remodel (e) classrooms spaces, restroom, office & storage on 1st floor. new partitions, lighting, electrical, mechanical, plumning, cabinets & finishes. remodel (e) lift & installation of new elevator to improve access. (2-stop elevator between 1st & 2nd floors).Details
remodel (e) classrooms spaces, restroom, office & storage on 1st floor. new partitions, lighting, electrical, mechanical, plumning, cabinets & finishes. remodel (e) lift & installation of new elevator to improve access. (2-stop elevator between 1st & 2nd floors). | $1,000,000 |
| Mar 22, 2010 | Completed final sign-off May 2011 | 3301 Lyon St | revision to pa# 2007-0724-7625-new landscaping, paving, pedestrian lighting & irrigationDetails
revision to pa# 2007-0724-7625-new landscaping, paving, pedestrian lighting & irrigation | ||
| May 29, 2008 | Completed final sign-off Aug 2008 | 2129 Vallejo St | San Francisco Commercial Builders Inc | remove (e) center handrail at exterior foyer. revision to handrail configuration and re-surface floor at entry and reception. reconfiguration of 2 (e) classrooms and 1 (e) office on the 2nd floor into 3 classroomsDetails
remove (e) center handrail at exterior foyer. revision to handrail configuration and re-surface floor at entry and reception. reconfiguration of 2 (e) classrooms and 1 (e) office on the 2nd floor into 3 classrooms | $100,000 |
| Nov 9, 2006 | Completed final sign-off Jan 2007 | 2120 Broadway | Plant Construction Company Lp | revision to approved building permit application #200605181932 delete fire resistive 1 hour coating @ new lateral canterlever columns for porte cochere.Details
revision to approved building permit application #200605181932 delete fire resistive 1 hour coating @ new lateral canterlever columns for porte cochere. |