- Apr 2019 to Nov 2025
10 permits since 2000 (architect on 10 permits): 7 completed, 2 in progress, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 25, 2025 | In progress issued Feb 2026 | 201 Filbert St | Anderson, Rowe & Buckley, Inc. | removal of e fire hose cabinets, floors 1-7. e gr fl exterior standpipes will be remain in place with caps welded in place to ensure they are never used again. infill wall openings at removed fire hose cabinetsDetails
removal of e fire hose cabinets, floors 1-7. e gr fl exterior standpipes will be remain in place with caps welded in place to ensure they are never used again. infill wall openings at removed fire hose cabinets | $50,000 |
| Nov 14, 2025 | In progress issued Feb 2026 | 201 Filbert St | Bcci Construction Company | 6th fl: minor work to construct an open coffee lounge, 2 phone rooms & demised lobby/reception area. work includes new non bearing partitions. 2 new doors, new lighting flooring, millwork, sink and paint. elec & telecom outlets & fls devices will be added to accommodate reconfiguration.Details
6th fl: minor work to construct an open coffee lounge, 2 phone rooms & demised lobby/reception area. work includes new non bearing partitions. 2 new doors, new lighting flooring, millwork, sink and paint. elec & telecom outlets & fls devices will be added to accommodate reconfiguration. | $175,000 |
| Mar 13, 2025 | Expired or cancelled expired Jun 2026 | 201 Filbert St | Capitol Electric Const | 1st floor: relocation of e fire smoke (manual fan and damper panel from lobby of bldg to adjacent fire annunciator roomDetails
1st floor: relocation of e fire smoke (manual fan and damper panel from lobby of bldg to adjacent fire annunciator room | $11,970 |
| Dec 30, 2024 | Completed final sign-off Apr 2025 | 201 Filbert St | Bcci Construction Company | 2nd fl: minor work to enclose an (e) coffee room & create (n) work room & conference room. limited demo, (n) non load bearing partitions, (2) new doors, additional electrical & telecom outlets, new flooring & replacement of floor; lights with new led lights. relocate fire sprinkelrs & horn strobesDetails
2nd fl: minor work to enclose an (e) coffee room & create (n) work room & conference room. limited demo, (n) non load bearing partitions, (2) new doors, additional electrical & telecom outlets, new flooring & replacement of floor; lights with new led lights. relocate fire sprinkelrs & horn strobes | $200,000 |
| Jul 23, 2024 | Completed final sign-off Dec 2024 | 201 Filbert St | Bcci Construction Company | 3rd floor: soft demo work & disabled access upgrade to toilet rms on vacant fl. demo work is specific to toilet rooms & limited areas within the interior of the office suite. work includes partial ht. partition, millwork & floor finishes demo, replacement of incondesent/ florescent light fixtureDetails
3rd floor: soft demo work & disabled access upgrade to toilet rms on vacant fl. demo work is specific to toilet rooms & limited areas within the interior of the office suite. work includes partial ht. partition, millwork & floor finishes demo, replacement of incondesent/ florescent light fixture | $319,043 |
| Feb 2, 2024 | Completed final sign-off Oct 2024 | 201 Filbert St | Bcci Construction Company | 6th fl: soft demo work throughout fl. includig removal of suspended clg. system, lgt fixtures & ceiling ht. partitions. upgrade toilet rooms to include accessible compliance, plmg fixture, interior finishes, & ltg upgrades. upgrade at ext perimeter offices to include nw suspended clg. system.Details
6th fl: soft demo work throughout fl. includig removal of suspended clg. system, lgt fixtures & ceiling ht. partitions. upgrade toilet rooms to include accessible compliance, plmg fixture, interior finishes, & ltg upgrades. upgrade at ext perimeter offices to include nw suspended clg. system. | $394,826 |
| Feb 2, 2024 | Completed final sign-off Oct 2024 | 201 Filbert St | Bcci Construction Company | 7th fl: soft demo work throughout fl. includig removal of suspended clg. system, lgt fixtures & ceiling ht. partitions. upgrade toilet rooms to include accessible compliance, plmg fixture, interior finishes, & ltg upgrades. upgrade at ext perimeter offices to include nw suspended clg. system.Details
7th fl: soft demo work throughout fl. includig removal of suspended clg. system, lgt fixtures & ceiling ht. partitions. upgrade toilet rooms to include accessible compliance, plmg fixture, interior finishes, & ltg upgrades. upgrade at ext perimeter offices to include nw suspended clg. system. | $428,626 |
| Sep 19, 2022 | Completed final sign-off Feb 2023 | 201 Filbert St | Bcci Construction Company | amendment to 202206236950 for phase 2 ti improvements in tenant suites 200 & 201. new interior partions, new elec & telecom outlets, new suspended clg. syste, new led lighting, relocated hvac diffusers & t-stats, relocated doors in new frames, new millwork...Details
amendment to 202206236950 for phase 2 ti improvements in tenant suites 200 & 201. new interior partions, new elec & telecom outlets, new suspended clg. syste, new led lighting, relocated hvac diffusers & t-stats, relocated doors in new frames, new millwork... | $700,000 |
| Jun 23, 2022 | Completed final sign-off Feb 2023 | 201 Filbert St | Bcci Construction Company | ste 200: soft demo 1 of 2 (e) vacant suites. remove ceiling & light fixtures in common corridor, elevator lobby & ste 200. upgrades in both men's & women's toilet rooms including accessible compliance upgrades, lights & finishes. sprinkler under pa# 202206156368.Details
ste 200: soft demo 1 of 2 (e) vacant suites. remove ceiling & light fixtures in common corridor, elevator lobby & ste 200. upgrades in both men's & women's toilet rooms including accessible compliance upgrades, lights & finishes. sprinkler under pa# 202206156368. | $300,000 |
| Apr 18, 2019 | Completed final sign-off Oct 2019 | 201 Filbert St | Skyline Construction | upgrade (e) elevator lobbies on floors 4, 6 & 7 to provide/install new smoke curtains at elevator doors. work is fire/life-safety upgrade to bring new elevator lobbies into code compliance.Details
upgrade (e) elevator lobbies on floors 4, 6 & 7 to provide/install new smoke curtains at elevator doors. work is fire/life-safety upgrade to bring new elevator lobbies into code compliance. | $150,000 |