Permit 202511129357

1201 Illinois St

potrero power plant development agreement priority. construction of exterior facade-visual moch up for power station block 2 (clinical life science building). structure is temporary (2 to 3 years) and non-occupiable.

Outcome
Completed (city status: complete, Oct 14, 2026)
Filed
Dec 3, 2025
Permit issued
Dec 29, 2025
Final sign-off
Oct 14, 2026
Declared cost
$745,000
Building use
power plant
Neighborhood
Potrero Hill (how long permits take there)
Contractor
Webcor Construction Lp (license 1037217)
Property
All permits at this address (block 4175, lot 017)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Webcor Construction Lp (license 1037217)
Architect
Stephani Chu, Stantec Architecture Inc. (license C39648)
Engineer
George Rogers, Mka (license C73602)
Pmt consultant/expediter
Nick Cereghino, A.R.Sanchez (no license listed), applicant