Permit GraphShortlistSan Francisco building permits since 2000

Permit 202509155268

138 Parker Av

relocate 3 fire sprinkler heads cibbect to (e) system per ti 202505216958, 201606270973

Outcome
Completed (city status: complete, May 27, 2026)
Filed
Sep 15, 2025
Permit issued
Sep 15, 2025
Final sign-off
May 27, 2026
Declared cost
$1,863
Building use
1 family dwelling
Neighborhood
Presidio Heights (how long permits take there)
Contractor
Sf Plumbing & Fire Protection Inc (license 1075806)
Property
All permits at this address (block 1065, lot 040)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Sf Plumbing & Fire Protection Inc (license 1075806)
Authorized agent
Ramon Estevez (no license listed), applicant