Permit 202508062449
550 Terry A Francois Bl
temporary lobby at level 1 to facilitate building entry and access to levels 5 and 6 once they are complete. during which the time levels 1-4 will still be under construction.
- Outcome
- Completed (city status: complete, Aug 12, 2026)
- Filed
- Aug 6, 2025
- Permit issued
- Sep 22, 2025
- Final sign-off
- Aug 12, 2026
- Declared cost
- $100,000
- Building use
- office
- Neighborhood
- Mission Bay
- Contractor
- Principal Builders Inc. (license 829808)
- Property
- All permits at this address (block 8721, lot 011)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Principal Builders Inc. (license 829808)
- Architect
- Patrick Daly (license C29703)
- Authorized agent-others
- David Lu (no license listed), applicant