Permit 202504174686

594 Vermont St

adjust outside air air volume for (e) furnace due to occupancy change; install new ductwork and air outlet; replace (e) condenser; install new lighting & switches, receptacles ref 202502100053

Outcome
Completed (city status: complete, Dec 9, 2025)
Filed
Apr 17, 2025
Permit issued
Apr 24, 2025
Final sign-off
Dec 9, 2025
Declared cost
$30,000
Building use
barber/beauty salon
Neighborhood
Potrero Hill
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 4011, lot 025)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder
Engineer
Charles Li, S & A Engineering Design (license C024211)
Designer
Sherman Yan (no license listed), applicant