Permit 202502210771

730 Montgomery St

on the first floor full tenant improvement on the second floor. new partial interior improvement mezzanine at the 2nd floor. new finishes, fixtuires, partitions, doors glazing, ceiling. mep deferred.

Outcome
Completed (city status: complete, Oct 10, 2025)
Filed
Feb 21, 2025
Permit issued
Mar 5, 2025
Final sign-off
Oct 10, 2025
Declared cost
$600,000
Building use
office
Neighborhood
Chinatown (how long permits take there)
Contractor
Novo Construction Inc (license 791022)
Property
All permits at this address (block 0196, lot 015)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Novo Construction Inc (license 791022)
Architect
Michael Dubitski (license C35493)
Authorized agent
Cyndi Batson (no license listed), applicant
Authorized agent
Mahmoud Larizadeh (no license listed), applicant