Permit 202401254691
50 08th St
installation of 6 tritium dc fast chargers to supply 12 publicly accesible dc fast charging stalls in hotel garage.ext of bus bar from (e) 4000a 120/208v switchboard to new 2500a/490v ac disconnect.install 750kva 208-480v step up transformer,new 1200a/480v evcs switchboard and 2 tritium power cabs.
- Outcome
- In progress (city status: filed, Apr 2, 2024)
- Filed
- Apr 2, 2024
- Declared cost
- $350,000
- Building use
- residential hotel
- Neighborhood
- South of Market
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 3701, lot 060)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Engineer
- John Bachoua, Nazarene Engineering (license E19677)
- Authorized agent-others
- Greg Evans (no license listed), applicant