Permit 202310269565
591 Vermont St
revision to permit# 202307031404: add (2) sheer walls with grade beam and anchor bolts. (10) new post footing with new post. wrap (6) (e) poles with 2 x 12 treated and bolted and nailed in place.
- Outcome
- Completed (city status: complete, Dec 13, 2024)
- Filed
- Oct 26, 2023
- Permit issued
- Nov 2, 2023
- Final sign-off
- Dec 13, 2024
- Declared cost
- $22,500
- Building use
- apartments
- Neighborhood
- Potrero Hill
- Contractor
- Handelin Inc Dba Original Construction C (license 330458)
- Property
- All permits at this address (block 4010, lot 005)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Handelin Inc Dba Original Construction C (license 330458), applicant
- Engineer
- Peter Culley, Consulting Engineer Llc (license S1969)