Permit 202306129865
408 Cortland Av
to comply w/ abe program 202205160825 and all work complete. see attached abe report
- Outcome
- Completed (city status: complete, Aug 9, 2023)
- Filed
- Jun 12, 2023
- Permit issued
- Jun 23, 2023
- Final sign-off
- Aug 9, 2023
- Building use
- food/beverage hndlng
- Neighborhood
- Bernal Heights
- Contractor
- Gil Construction & Assoc Inc. (license 703705)
- Property
- All permits at this address (block 5678, lot 025)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Gil Construction & Assoc Inc. (license 703705)
- Authorized agent-others
- Melissa Gil, Gil Construction (no license listed), applicant