Permit GraphShortlistSan Francisco building permits since 2000

Permit 202208261410

22 Flint St

lower unit only (22f): replace (e) in-wall electric heaters with new hydronic heating system.

Outcome
Completed (city status: complete, Nov 14, 2023)
Filed
Aug 26, 2022
Permit issued
Sep 21, 2022
Final sign-off
Nov 14, 2023
Declared cost
$15,000
Building use
2 family dwelling
Neighborhood
Castro/Upper Market
Contractor
Urban Builder General Contracting Inc (license 869710)
Property
All permits at this address (block 2614, lot 097)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Urban Builder General Contracting Inc (license 869710)
Designer
Alan Tse, Alan Tse Design (no license listed), applicant