Permit 202207188688
4901 03rd St
to comply with nov 202065461. new as-built drawings of (n) storefront work, completed without a permit.
- Outcome
- Completed (city status: complete, Mar 23, 2023)
- Filed
- Jul 18, 2022
- Permit issued
- Feb 6, 2023
- Final sign-off
- Mar 23, 2023
- Declared cost
- $5,000
- Building use
- retail sales
- Neighborhood
- Bayview Hunters Point
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 5326, lot 012)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Architect
- Julio Guerrero (license C38612), applicant
- Lessee
- Saleh Ahmed (no license listed)