Permit 202107023718
201 Girard St
add a 2nd unit: convert at 1st floor to livng space:install new furnace and water heater.
- Outcome
- Completed (city status: complete, Mar 30, 2022)
- Filed
- Jul 2, 2021
- Permit issued
- Jul 28, 2021
- Final sign-off
- Mar 30, 2022
- Declared cost
- $39,000
- Building use
- 2 family dwelling
- Neighborhood
- Portola
- Contractor
- Hutan Construction (license 1051203)
- Property
- All permits at this address (block 5981, lot 024)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Hutan Construction (license 1051203)
- Owner-builder
- Owner Builder
- Authorized agent-others
- Sunny Gao (no license listed)