Permit GraphShortlistSan Francisco building permits since 2000

Permit 202106041692

2300 26th St

remove and replace 3 at&t antennas, remove and replace 3 rrus, install 3 diplexers, remove 2 (e) rbs 226 cabinets, install 3 ge rectifier in dc power plant, remove/repl batt racks, install 8 new batteries. separate operating permit for batteries.

Outcome
Completed (city status: complete, Oct 19, 2021)
Filed
Jun 4, 2021
Permit issued
Sep 8, 2021
Final sign-off
Oct 19, 2021
Declared cost
$20,000
Building use
office
Neighborhood
Potrero Hill (how long permits take there)
Contractor
Ericsson Inc Dba E U S Inc (license 698896)
Property
All permits at this address (block 4280, lot 025)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Ericsson Inc Dba E U S Inc (license 698896)
Engineer
Chris Lee (license 76549)
Authorized agent
Jossseline Diaz (no license listed)