Permit 201909131662
1142 Mariposa St
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4
- Outcome
- Completed (city status: complete, Jul 24, 2020)
- Filed
- Sep 13, 2019
- Permit issued
- Oct 7, 2019
- Final sign-off
- Jul 24, 2020
- Declared cost
- $180,000
- Building use
- apartments
- Neighborhood
- Potrero Hill
- Contractor
- Hyan Construction Company (license 880366)
- Property
- All permits at this address (block 3986, lot 011)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Hyan Construction Company (license 880366), applicant
- Engineer
- Stephen Chan, Stephen Chan Consulting Eng. (license S4533)