Permit GraphShortlistSan Francisco building permits since 2000

Permit 201908017597

922 Post St

to obtain final inspection for work approved under pa# 201708084162. all work is complete. to comply with nov 201773502

Outcome
Completed (city status: complete, Aug 20, 2019)
Filed
Aug 1, 2019
Permit issued
Aug 1, 2019
Final sign-off
Aug 20, 2019
Building use
apartments
Neighborhood
Nob Hill
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 0301, lot 008)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder