Permit 201906284706
4526 03rd St
cannabis dispensery t.i. scope with selective demolition of extg non-structural wall, construction of new non structural wall and associated mech, plmg, electrical, and finishes. mep scope to be deferred submittal.
- Outcome
- Completed (city status: complete, Mar 23, 2021)
- Filed
- Jun 28, 2019
- Permit issued
- Nov 26, 2019
- Final sign-off
- Mar 23, 2021
- Declared cost
- $85,000
- Building use
- retail sales
- Neighborhood
- Bayview Hunters Point (how long permits take there)
- Contractor
- Vsa Construction (license 990233)
- Property
- All permits at this address (block 5296, lot 020)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Vsa Construction (license 990233), applicant
- Architect
- Tuon Louv, Hood Thomas Architects (no license listed)
- Lessee
- Cdxx Llc (no license listed)