Permit 201904097476
3001 Sacramento St
seismic soft story retrofit per sfebc ch 4d, engineering criteria 2016 cebc appendix a-4. residential
- Outcome
- Completed (city status: complete, Dec 10, 2019)
- Filed
- Apr 9, 2019
- Permit issued
- Aug 27, 2019
- Final sign-off
- Dec 10, 2019
- Declared cost
- $71,400
- Building use
- apartments
- Neighborhood
- Pacific Heights
- Contractor
- Sft Construction Corp (license 1009086)
- Property
- All permits at this address (block 1024, lot 001)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Sft Construction Corp (license 1009086)
- Authorized agent-others
- Farim Ghandi, Sft Construction Corpfars (no license listed), applicant