Permit 201901140236
222 Kearny St
ref pa# 201809119708; mechanical & electrical. 7th and 9th floor, provide 6(n) vav boxes, with reheat coils. (5) new fan coils @ 7th and 9th floor. (1) new air cooled unit on roof.
- Outcome
- Completed (city status: complete, May 8, 2019)
- Filed
- Jan 14, 2019
- Permit issued
- Jan 30, 2019
- Final sign-off
- May 8, 2019
- Declared cost
- $600,000
- Building use
- office
- Neighborhood
- Financial District/South Beach
- Contractor
- M C S Construction Services (license 1015908)
- Property
- All permits at this address (block 0288, lot 029)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- M C S Construction Services (license 1015908)
- Engineer
- Gregory Mcmanus, Randall Lamb Engineers (no license listed)
- Lessee
- Nw Llc (no license listed)