Permit GraphShortlistSan Francisco building permits since 2000

Permit 201812128116

4428 23rd St

horizontal and vertical addition at rear. change to facade. addition of garage/garage door.

Outcome
Completed (city status: complete, Jan 16, 2024)
Filed
Dec 12, 2018
Permit issued
Jan 30, 2021
Final sign-off
Jan 16, 2024
Declared cost
$500,000
Building use
1 family dwelling
Neighborhood
Noe Valley (how long permits take there)
Contractor
Basset Engineering (license 1070288), Kilrea Construction Inc. (license 924033)
Property
All permits at this address (block 2801, lot 011)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Basset Engineering (license 1070288)
Contractor
Kilrea Construction Inc. (license 924033)
Architect
Setareh Taghvaei, Brooks Mcdonald (no license listed)