Permit GraphShortlistSan Francisco building permits since 2000

Permit 201808278395

345 Fulton St

apt 32: opening dry walls, rough electrical and final, closing back dry wall when all done. maher n/a.

Outcome
Completed (city status: complete, Nov 7, 2018)
Filed
Aug 27, 2018
Permit issued
Aug 27, 2018
Final sign-off
Nov 7, 2018
Declared cost
$8,000
Building use
apartments
Neighborhood
Hayes Valley
Contractor
B-Side Inc. (license 821091)
Property
All permits at this address (block 0792, lot 007A)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
B-Side Inc. (license 821091), applicant