Permit GraphShortlistSan Francisco building permits since 2000

Permit 201803193958

680 Folsom St

mep for ti provide & install vav terminal boxes including duct work & piping & electrical work. ref pa 2018-0208-0728

Outcome
Completed (city status: complete, Jun 13, 2018)
Filed
Mar 19, 2018
Permit issued
Apr 10, 2018
Final sign-off
Jun 13, 2018
Declared cost
$40,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Novo Construction Inc (license 791022)
Property
All permits at this address (block 3735, lot 013)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Novo Construction Inc (license 791022)
Lessee
Riverbeel (no license listed)
Pmt consultant/expediter
Cyndi Batson/ Lori Thompson (no license listed), applicant