Permit 201801168735
342 Grant Av
provide supplemental structural work for the lobby ceiling design approved under 201711274802 maher na
- Outcome
- Never finaled (city status: issued, Jan 29, 2018)
- Filed
- Jan 16, 2018
- Permit issued
- Jan 29, 2018
- Declared cost
- $5,000
- Building use
- tourist hotel/motel
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 0287, lot 017)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner