Permit 201712206937
900 Marin St
1 sheet revision to 201312305291 - remove ada lift,provide new ada ramp to stage. per correction notive by senior inspectro bernie curran, as-builts filed under separate permit. sheet a1 .03 maher na
- Outcome
- Completed (city status: complete, Dec 21, 2017)
- Filed
- Dec 20, 2017
- Permit issued
- Dec 20, 2017
- Final sign-off
- Dec 21, 2017
- Declared cost
- $2,000
- Building use
- theater
- Neighborhood
- Bayview Hunters Point (how long permits take there)
- Contractor
- None listed with a license number
- Property
- All permits at this address (block 4357, lot 003)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Engineer
- Rodrigo Santos, Rs Engineering (license S2984)
- Authorized agent
- Rodrigo Santos (no license listed), applicant