Permit 201712196870

635 Fulton St

new foundation and mep to prepare site for two (e) moved buildings, two (e) moved buildings to comply w/ cbc 503.1.2 as one building.

Outcome
Completed (city status: complete, Feb 21, 2024)
Filed
Dec 19, 2017
Permit issued
Dec 31, 2018
Final sign-off
Feb 21, 2024
Declared cost
$3,900,000
Building use
apartments
Neighborhood
Hayes Valley
Contractor
An Dun Construction (license 919465)
Property
All permits at this address (block 0795, lot 027)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
An Dun Construction (license 919465)
Owner-builder
Owner Builder
Architect
Edward Toby Morris, Kerman Morris Architects (license C24585)
Architect
Edward"Toby" Morris (license C24585)
Authorized agent-others
Jules Mancilla (no license listed), applicant
Authorized agent-others
Kerman Morris Arch (no license listed)