Permit 201712136313

351 Harriet St

install new ada bathrooms, new ada ramp and new stair. maher ord 155-13 na

Outcome
Completed (city status: complete, Jun 20, 2018)
Filed
Dec 13, 2017
Permit issued
Jan 16, 2018
Final sign-off
Jun 20, 2018
Declared cost
$20,000
Building use
manufacturing
Neighborhood
South of Market
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Project type
Stairs, Bathroom remodel
Property
All permits at this address (block 3779, lot 120)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder, applicant
Architect
Gary Gee, Gary Gee Architects, Inc. (license C14060)