Permit 201708235627
2595 Clay St
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4.
- Outcome
- Completed (city status: complete, Sep 25, 2018)
- Filed
- Aug 23, 2017
- Permit issued
- Aug 29, 2017
- Final sign-off
- Sep 25, 2018
- Declared cost
- $45,000
- Building use
- apartments
- Neighborhood
- Pacific Heights
- Contractor
- Sft Construction Corp (license 1009086)
- Property
- All permits at this address (block 0630, lot 033)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Sft Construction Corp (license 1009086)
- Engineer
- Erevan O'neill, One Design (license C75459)