Permit 201707202430
1200 Francisco St
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4. all work in garage, adding plywood to (e) walls, install new shearwalls, foundation work includes adding a new grade beam at new shearwalls and install holdowns into existing foundation.
- Outcome
- Completed (city status: complete, Aug 21, 2018)
- Filed
- Jul 20, 2017
- Permit issued
- Aug 22, 2017
- Final sign-off
- Aug 21, 2018
- Declared cost
- $150,000
- Building use
- apartments
- Neighborhood
- Marina
- Contractor
- Jari Construction Inc (license 963722)
- Property
- All permits at this address (block 0474, lot 005)