Permit 201603242972
185 Berry St
level #4 phase 2 (east half) - (318) added fire sprinklers. ref pa #201412194129.
- Outcome
- Completed (city status: complete, Jul 7, 2017)
- Filed
- Mar 24, 2016
- Permit issued
- Apr 5, 2016
- Final sign-off
- Jul 7, 2017
- Declared cost
- $163,400
- Building use
- office
- Neighborhood
- Mission Bay
- Contractor
- Allied Fire Protection (license 251700)
- Property
- All permits at this address (block 3803, lot 001)