Permit GraphShortlistSan Francisco building permits since 2000

Permit 201601147160

1200 Mississippi St

to obtain final inspection for work approved under pa#201407302574. all work is complete.

Outcome
Completed (city status: complete, Feb 22, 2016)
Filed
Jan 14, 2016
Permit issued
Jan 14, 2016
Final sign-off
Feb 22, 2016
Building use
office
Neighborhood
Bayview Hunters Point (how long permits take there)
Contractor
L Cabral Construction (license 996081)
Property
All permits at this address (block 4288, lot 003)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
L Cabral Construction (license 996081), applicant