Permit GraphShortlistSan Francisco building permits since 2000

Permit 201512145049

888 Brannan St

mechanical work install 1 new daikin water source heat pump. relocate thermostat. compliance with maher ordinance no 155-13 not required.

Outcome
Completed (city status: complete, Mar 17, 2016)
Filed
Dec 14, 2015
Permit issued
Dec 28, 2015
Final sign-off
Mar 17, 2016
Declared cost
$10,000
Building use
office
Neighborhood
South of Market (how long permits take there)
Contractor
Novo Construction Inc (license 791022)
Property
All permits at this address (block 3780, lot 006)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Novo Construction Inc (license 791022)
Engineer
O.David Vazquez Camacho, Allied Heating & Air Con (license M32731)
Authorized agent
Cyndi Batson/ Lori Thompson, Novo Construction (no license listed), applicant
Lessee
Air B N B (no license listed)