Permit 201504274736
611 Front St
construct new elevator controller room, basement level. fire alarm and electrical work under sep permit
- Outcome
- Completed (city status: complete, May 21, 2015)
- Filed
- Apr 27, 2015
- Permit issued
- Apr 30, 2015
- Final sign-off
- May 21, 2015
- Declared cost
- $3,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- P Power Construction (license 966012)
- Property
- All permits at this address (block 0173, lot 005)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- P Power Construction (license 966012)
- Architect
- Aston Pereira, Aston Perreira & Associates (license C12756)