Permit 201504274641
185 Berry St
6th floor: tie in new branch lines to the extg mains. mains installed under app#201411070971. 683 sprinkler heads.
- Outcome
- Completed (city status: complete, Feb 10, 2017)
- Filed
- Apr 27, 2015
- Permit issued
- Apr 27, 2015
- Final sign-off
- Feb 10, 2017
- Declared cost
- $200,000
- Building use
- office
- Neighborhood
- Mission Bay
- Contractor
- Allied Fire Protection (license 251700)
- Property
- All permits at this address (block 3803, lot 001)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Allied Fire Protection (license 251700), applicant