Permit GraphShortlistSan Francisco building permits since 2000

Permit 201310098939

249 Cherry St

to obtain final inspection for work approved under pa# 200906170625 all work is complete.

Outcome
Never finaled (city status: issued, Oct 9, 2013)
Filed
Oct 9, 2013
Permit issued
Oct 9, 2013
Building use
1 family dwelling
Neighborhood
Presidio Heights (how long permits take there)
Contractor
Moroso Construction Inc (license 780511)
Property
All permits at this address (block 0991, lot 005)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Moroso Construction Inc (license 780511), applicant