Permit GraphShortlistSan Francisco building permits since 2000

Permit 201308225031

18 Ramona Av

kitchen remodel; replace countertops, installation of hardwood floor (cabinets to remain); replace water heater & furnace; to comply with cec 150(k) 8

Outcome
Completed (city status: complete, Oct 9, 2013)
Filed
Aug 22, 2013
Permit issued
Aug 23, 2013
Final sign-off
Oct 9, 2013
Declared cost
$9,000
Building use
2 family dwelling
Neighborhood
Mission (how long permits take there)
Contractor
Salgo Constructions (license 926493)
Project type
Kitchen remodel
Property
All permits at this address (block 3545, lot 109)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Salgo Constructions (license 926493), applicant