Permit 201101108125
2050 Lyon St
upgrade of kitchen - new tile floor, new cabinets and countertop. electrical - new subpanel, add 220 circuit
- Outcome
- Completed (city status: complete, Apr 22, 2011)
- Filed
- Jan 10, 2011
- Permit issued
- Jan 10, 2011
- Final sign-off
- Apr 22, 2011
- Declared cost
- $20,000
- Building use
- apartments
- Neighborhood
- Pacific Heights
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Project type
- Kitchen remodel
- Property
- All permits at this address (block 0999, lot 057)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder