Permit 201004220840
3322 Washington St
new supervised fire sprinkler monitoring. install 1 slave fire communicator, 1 smoke detector, 1 pull station, 2 connections to existing waterflow and gate valve
- Outcome
- Completed (city status: complete, Aug 17, 2010)
- Filed
- Apr 22, 2010
- Permit issued
- Apr 22, 2010
- Final sign-off
- Aug 17, 2010
- Declared cost
- $1,500
- Building use
- apartments
- Neighborhood
- Presidio Heights (how long permits take there)
- Contractor
- San Francisco Fire Protection (license 806216)
- Property
- All permits at this address (block 0984, lot 026)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- San Francisco Fire Protection (license 806216), applicant