Permit 200505203031

240 Stockton St

oti-1, 3rd floor, light, me, ls, sp.

Outcome
Completed (city status: complete, Feb 22, 2006)
Filed
May 20, 2005
Permit issued
May 31, 2005
Final sign-off
Feb 22, 2006
Declared cost
$20,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Principal Builders Inc. (license 829808)
Property
All permits at this address (block 0309, lot 020)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Principal Builders Inc. (license 829808)
Authorized agent
Lindy Yu, Principal Builders (no license listed), applicant