85 permits since 2000: 66 completed, 14 never finaled, 5 expired or cancelled.
Of the 14 never-finaled permits, 1 is 5 to 10 years old, 13 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Bathroom remodel permits
22 bathroom remodel permits: 17 completed, 2 never finaled, 3 expired or cancelled. Typically 6 days from filing to permit and 210 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Feb 9, 2017 | Completed final sign-off Jun 2017 | 54 Landers St | to partially comply with physical inspection report #cc-7949, item #11 for bathroom portion (kitchen remodel pa#201604043795); any lighting change high efficacy or sensor occupant controlled.Details
to partially comply with physical inspection report #cc-7949, item #11 for bathroom portion (kitchen remodel pa#201604043795); any lighting change high efficacy or sensor occupant controlled. | $6,000 |
| Apr 15, 2016 | Expired or cancelled cancelled Feb 2020 | 873 Ashbury St | 3rd story addition, demo of rotting & unsafe wood deck, beams & stair. remodel inside (e) envelope of 873 ashbury & partial 3rd story addition, adding bathroom. widen garage door.Details
3rd story addition, demo of rotting & unsafe wood deck, beams & stair. remodel inside (e) envelope of 873 ashbury & partial 3rd story addition, adding bathroom. widen garage door. | $100,000 |
| Jul 8, 2015 | Completed final sign-off Oct 2015 | 117 Robinhood Dr | remodel of 1 kitchen and 4 bathrooms.Details
remodel of 1 kitchen and 4 bathrooms. | $30,000 |
| Jun 10, 2015 | Completed final sign-off Jul 2016 | 2711 Union St | replace kitchen, powder room & two bathrooms. add wet bar to family room @ 3rd floor, change windows to doors @ 1st & 3rd floors as noted. replace door 1st floor, reconfigure master bedroom closets.Details
replace kitchen, powder room & two bathrooms. add wet bar to family room @ 3rd floor, change windows to doors @ 1st & 3rd floors as noted. replace door 1st floor, reconfigure master bedroom closets. | $100,000 |
| Jun 10, 2015 | Completed final sign-off Sep 2015 | 321 Lake St | infill lightwell, renovate 2/f bathrooms.Details
infill lightwell, renovate 2/f bathrooms. | $50,000 |
| Apr 6, 2015 | Completed final sign-off Aug 2017 | 2942 Polk St | 1st flr: add nw bedroom, nw bathroom,& nw staircase. 2nd fl:add nw bathroom, remodel extg bathroom, remodel extg kitchen, 3rd fl:add nw bathroom, remodel extg bathrm, remodel extg kchnDetails
1st flr: add nw bedroom, nw bathroom,& nw staircase. 2nd fl:add nw bathroom, remodel extg bathroom, remodel extg kitchen, 3rd fl:add nw bathroom, remodel extg bathrm, remodel extg kchn | $100,000 |
| Jun 26, 2014 | Completed final sign-off Dec 2014 | 148 Ulloa St | interior renovation including new family room at ground; remodel (e) bath, replace (e) french door @ rear w/new , new window @ east elevation, repl (e) window @west elevation with new, repl(e) door @ west with newDetails
interior renovation including new family room at ground; remodel (e) bath, replace (e) french door @ rear w/new , new window @ east elevation, repl (e) window @west elevation with new, repl(e) door @ west with new | $30,000 |
| May 13, 2014 | Completed final sign-off Apr 2015 | 1892 Green St | demolition & remodel of existing kitchen & bathroom. removal of structural wall install beam & supports@ third floorDetails
demolition & remodel of existing kitchen & bathroom. removal of structural wall install beam & supports@ third floor | $50,000 |
| Apr 18, 2014 | Completed final sign-off Jul 2014 | 187 Elsie St | bathroom remodelDetails
bathroom remodel | $10,000 |
| Dec 6, 2013 | Completed final sign-off Jul 2014 | 1835 Franklin St | kitchen and 2 bath remodel, new flooringDetails
kitchen and 2 bath remodel, new flooring | $50,000 |
| Dec 6, 2013 | Completed final sign-off Aug 2020 | 2551 Greenwich St | move garage door to front, add door to entry. remodel stairs to upper unit. remodel bathrooms @ 2nd floor. add stairs to new 3rd floor. add 3rd floor to enlarge upper unit. add stairs to new roof deck.Details
move garage door to front, add door to entry. remodel stairs to upper unit. remodel bathrooms @ 2nd floor. add stairs to new 3rd floor. add 3rd floor to enlarge upper unit. add stairs to new roof deck. | $350,000 |
| Jun 6, 2013 | Expired or cancelled expired Jun 2017 | 440 Molimo Dr | kitchen remodel and bath remodelDetails
kitchen remodel and bath remodel | $40,000 |
| May 30, 2013 | Completed final sign-off Aug 2015 | 610 04th Av | 3 story rear addition, 1 story rear addition with deck above, new master bath, remove gas fireplace, remove non conforming breakfast roomDetails
3 story rear addition, 1 story rear addition with deck above, new master bath, remove gas fireplace, remove non conforming breakfast room | $130,000 |
| May 20, 2013 | Never finaled filed May 2013, never issued | 321 Lake St | infill under (e) porch to enlarge (e) bedroom, family room. kitchen and bath remodel on separate permitDetails
infill under (e) porch to enlarge (e) bedroom, family room. kitchen and bath remodel on separate permit | $150,000 |
| Jun 11, 2012 | Completed final sign-off Jul 2014 | 3855 25th St | rear addition: new living room +bathroom at ground floor, new stair from main level fown. new bathroom + enlarged bedrooms at top floor. total four new skylightsDetails
rear addition: new living room +bathroom at ground floor, new stair from main level fown. new bathroom + enlarged bedrooms at top floor. total four new skylights | $175,000 |
| Feb 16, 2012 | Completed final sign-off Feb 2014 | 2425 Ocean Av | one story addition on west side of building. converting garage to office space, and adding ada bathroom.Details
one story addition on west side of building. converting garage to office space, and adding ada bathroom. | $95,000 |
| Nov 3, 2011 | Never finaled issued Nov 2011, no final | 1040 Francisco St | voluntary seismic retrofitting at basement. legalize bedroom and bath on garage level.Details
voluntary seismic retrofitting at basement. legalize bedroom and bath on garage level. | $5,000 |
| Sep 12, 2011 | Completed final sign-off Mar 2012 | 1040 Francisco St | bathroom remodel, replace sink, toilet, tub, & tile with newDetails
bathroom remodel, replace sink, toilet, tub, & tile with new | $20,000 |
| Jul 5, 2011 | Completed final sign-off Sep 2011 | 65 Levant St | to comply w/ report cc-5450. garage: remove exposed facing materials and insulation. #65: sub bbsmnt: remove illegal kitchen and cabs, elec. htrs and cap sink, gas& plbb. legalize(add) bathroom and shower. #65,67: install smoke detectors. common area: install vacuum breakers at hose bibsDetails
to comply w/ report cc-5450. garage: remove exposed facing materials and insulation. #65: sub bbsmnt: remove illegal kitchen and cabs, elec. htrs and cap sink, gas& plbb. legalize(add) bathroom and shower. #65,67: install smoke detectors. common area: install vacuum breakers at hose bibs | $8,000 |
| May 23, 2011 | Completed final sign-off Oct 2011 | 25 San Anselmo Av | install new bathroom in extg basement. provide new clerestory fixed laminate glass window.Details
install new bathroom in extg basement. provide new clerestory fixed laminate glass window. | $18,000 |
| Mar 17, 2011 | Completed final sign-off Dec 2011 | 54 Forest Side Av | bathroom remodel, toilet stays, new pedestal, new walk in shower. (n) lighting & clg. fan & relocation of light switch & receptacle outlet.Details
bathroom remodel, toilet stays, new pedestal, new walk in shower. (n) lighting & clg. fan & relocation of light switch & receptacle outlet. | $2,500 |
| May 25, 2005 | Expired or cancelled expired Apr 2006 | 2416 Bush St | master bathroom remodel, moving non load bearing doors and adding door, fluorescent lightingDetails
master bathroom remodel, moving non load bearing doors and adding door, fluorescent lighting | $7,000 |