- 0 permits filed
12 permits since 2000: 7 completed, 4 never finaled, 1 expired or cancelled.
Of the 4 never-finaled permits, 4 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Bathroom remodel permits
4 bathroom remodel permits: 4 completed. Typically 1 days from filing to permit and 227 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Nov 16, 2009 | Completed final sign-off May 2010 | 92 Santa Marina St | renovate bathroom; add bathroom @ (e) closet/laundry room. in-fill (e) light well. add 3-skylights. 30" parapet @ skylight location per plan.Details
renovate bathroom; add bathroom @ (e) closet/laundry room. in-fill (e) light well. add 3-skylights. 30" parapet @ skylight location per plan. | $30,000 |
| Aug 28, 2009 | Completed final sign-off May 2010 | 412 Jersey St | retile & change fixtures in two bathrooms (faucets only). re-sheetrock garage 200 sq ft. install fluorescent lights in garage. service upgrade electrical 125a.Details
retile & change fixtures in two bathrooms (faucets only). re-sheetrock garage 200 sq ft. install fluorescent lights in garage. service upgrade electrical 125a. | $12,000 |
| Jul 7, 2009 | Completed final sign-off Nov 2009 | 65 Santa Clara Av | reface kitchen cabinets. partially repalce tiel on countertop in kitchen. partially replace tile in 2 bathrooms, refinish approximately 100 sq. ft. of handwood floor. no electrical and plumbing work. no lighting change.Details
reface kitchen cabinets. partially repalce tiel on countertop in kitchen. partially replace tile in 2 bathrooms, refinish approximately 100 sq. ft. of handwood floor. no electrical and plumbing work. no lighting change. | $1,200 |
| Nov 7, 2008 | Completed final sign-off Jun 2010 | 412 Jersey St | horizontal & vertical addition, 1st fl: remove 2 columns/replace w/ new. 2nd fl: remodel kitchen & bathrm, add new stair to 3rd fl, expand deck @ rear & add barrier wall. 3rd fl: add 3rd floor addition including master bedrm & bath, guest & bath, 2 lightwells and stair.full seismic upgrade.Details
horizontal & vertical addition, 1st fl: remove 2 columns/replace w/ new. 2nd fl: remodel kitchen & bathrm, add new stair to 3rd fl, expand deck @ rear & add barrier wall. 3rd fl: add 3rd floor addition including master bedrm & bath, guest & bath, 2 lightwells and stair.full seismic upgrade. | $275,000 |