- 0 permits filed
5 permits since 2000: 5 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Bathroom remodel permits
3 bathroom remodel permits: 3 completed. Typically 0 days from filing to permit and 63 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 10, 2012 | Completed final sign-off Apr 2013 | 301 Main St | no work to be performed on demising walls or fire walls. building is structural concrete floors & columns. lighting & plumbing permits by electrical contractor & plumbing contractor. scope of work includes kitchen cabinets, replace vanity, toilet, shower, bath to shoer conversion.Details
no work to be performed on demising walls or fire walls. building is structural concrete floors & columns. lighting & plumbing permits by electrical contractor & plumbing contractor. scope of work includes kitchen cabinets, replace vanity, toilet, shower, bath to shoer conversion. | $100,000 |
| Aug 21, 2008 | Completed final sign-off Oct 2008 | 301 Main St | install recessed can lights in entry hall, other hall guest bath, pdr rooms. master bath, master bed hall - rail light 5'. modify closet door to sliding. install new tile to guest bathrm floor. showerwalls & floor incl. waterprooof pan. install new top faucet vanity & toilet in guest bath.Details
install recessed can lights in entry hall, other hall guest bath, pdr rooms. master bath, master bed hall - rail light 5'. modify closet door to sliding. install new tile to guest bathrm floor. showerwalls & floor incl. waterprooof pan. install new top faucet vanity & toilet in guest bath. | |
| Apr 7, 2008 | Completed final sign-off Jun 2008 | 301 Main St | install new tile to shower&floor in #2 bathrm,chg shape. new vanity/top,shower door. custorm tile shower pan,new top on kitchen island.add lights in bathroom(3), in office(2), outlet incloset & office area, change size (36" to 32") & swing of bath door. add valance in mstr bed w/ back light.Details
install new tile to shower&floor in #2 bathrm,chg shape. new vanity/top,shower door. custorm tile shower pan,new top on kitchen island.add lights in bathroom(3), in office(2), outlet incloset & office area, change size (36" to 32") & swing of bath door. add valance in mstr bed w/ back light. | $50,000 |