Leo Gotelli Plumbing Inc
- Based in
- Brisbane
- On San Francisco permits
- Dec 2009 to Jul 2017
- Last 24 months
- 0 permits filed
4 permits since 2000: 1 completed, 3 never finaled.
Of the 3 never-finaled permits, 3 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 19, 2017 | Completed final sign-off Sep 2018 | 431 02nd Av | install 15 feet new underground piping per nfpa#24 to pa#201706018201 & 201701137193Details
install 15 feet new underground piping per nfpa#24 to pa#201706018201 & 201701137193 | $2,000 |
| Jul 19, 2010 | Never finaled issued Jul 2010, no final | 325 China Basin St | remove air storage & cap according to sffd ad507, remove tanks, remove comp. & com. pump, remove analizer panel system will only be supplied by outside fd. service panels. remove anaylizer associated fa monitor equipment.Details
remove air storage & cap according to sffd ad507, remove tanks, remove comp. & com. pump, remove analizer panel system will only be supplied by outside fd. service panels. remove anaylizer associated fa monitor equipment. | |
| Dec 23, 2009 | Never finaled issued Dec 2009, no final | 1310 Fillmore St | removing air storage system in accordance w/sffd ab507 and cap existing lines, remove air antalizer panel. all air will be supplie from sffd. tested from bauer co.Details
removing air storage system in accordance w/sffd ab507 and cap existing lines, remove air antalizer panel. all air will be supplie from sffd. tested from bauer co. | |
| Dec 23, 2009 | Never finaled issued Dec 2009, no final | 631 Folsom St | remove air storage & cap according to sffd ab-507. remove tanks, remove compressor & remove pressure pump. remove analizer panel. system will only be supplied by outside fd service panels.Details
remove air storage & cap according to sffd ab-507. remove tanks, remove compressor & remove pressure pump. remove analizer panel. system will only be supplied by outside fd service panels. |