J P L Construction
- Based in
- Oakland
- On San Francisco permits
- May 2009 to Jul 2011
- Last 24 months
- 0 permits filed
2 permits since 2000: 1 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 28, 2011 | Completed final sign-off Sep 2011 | 5800 03rd St | minor revision to approved pa# 2011-0201-9420-minor change to seating layout & reduction of occupancy loadDetails
minor revision to approved pa# 2011-0201-9420-minor change to seating layout & reduction of occupancy load | |
| May 12, 2009 | Never finaled issued May 2009, no final | 34 Aladdin Tr | replace 4 x 6 post with a new pt 4 x 6. install a new handrail & guardrails will be at 42" high handrail up the stairs will be at 36". fix all the dry rot for the stairs. install a35 & joist hangers where needed. under 50% repair. if repair beyond 50% will require plans.Details
replace 4 x 6 post with a new pt 4 x 6. install a new handrail & guardrails will be at 42" high handrail up the stairs will be at 36". fix all the dry rot for the stairs. install a35 & joist hangers where needed. under 50% repair. if repair beyond 50% will require plans. | $4,000 |